Publications

Alaska’s Natural Gas Pipeline: Closer to Reality? Resource Development Council Breakfast

Release Date: 
03/19/2009

 

Alaska Natural Gas Pipeline: Closer to Reality?
Resource Development Council Breakfast
Anchorage, Alaska
March 19, 2009

By Drue Pearce, Federal Coordinator
Office of the Federal Coordinator
Alaska Natural Gas Transportation Projects

SLIDE 1: Introduction Page
Good Morning—Thank you to Jason, Carl and RDC for having me address your breakfast. I would like to quickly introduce you to Christa Gunn. She is and Environmental Engineer, working on the OFC staff here in Anchorage. She arrived last month and has hit the ground running.
I’m here to tell you about the need for and challenges of getting Alaska’s North Slope natural gas to market. As all of you know, one of the largest known reserves of natural gas in America sits in Alaska’s Arctic, associated with the development of oil at Prudhoe Bay. The 35 trillion cubic feet of proven natural gas reserves will make a significant long-term contribution to the United States’ energy supplies. Since the late 1990’s, the State of Alaska, the three North Slope Producers, TransCanada, and other major pipeline companies have been pondering whether now is the time when construction of the gasline is economically feasible. CLICK

SLIDE 2: TAPS
Before TAPS was built in the early 1970’s there were countless environmental, arctic construction, and native subsistence and sovereignty challenges to be resolved. It took federal enactment of the ANCSA and TAPAA in order for construction to proceed. At the time, the necessary infrastructure did not exist. It all had to be built before pipeline construction could commence.
This project, a mostly buried, chilled, high pressure natural gas pipeline, brings a host of new challenges. CLICK
SLIDE 3: ANGTA
Although many of you may already know it, I think it is important to provide you with a brief history about the federal laws governing the gas pipeline project.
While TAPS was being constructed, plans were initiated to build a large diameter pipeline to deliver the associated natural gas to the lower 48. Congress enacted the Alaska Natural Gas Transportation Act and President Carter designated the route, design and project sponsors for this transportation system.
The southern portions of the pipeline shown in light green on this map are known as the “pre-build” and went into operation in 1981-1982. The northern portion shown in dark green, would link North Slope gas to the pre-built legs. Foothills Pipe Line Ltd, now a subsidiary of TransCanada, is the legacy owner and operator of the pre-build. The northern portion is the route of the pipeline that has remained an elusive target but irresistible dream to Alaskans. CLICK
SLIDE 4: ANGPA
There have been countless proposals to produce North Slope gas since the late 1970’s. The latest effort led to Congress passing the Alaska Natural Gas Pipeline Act, known as ANGPA in 2004. That statute created my office, the Office of the Federal Coordinator for Alaska Natural Gas Transportation Projects, and encouraged the expeditious approval, construction, and operation of a natural gas transportation project for delivery of North Slope gas to U.S. markets.

SLIDE 5: Planned Pipeline Projects
There are 4 projects that the Office of the Federal Coordinator is monitoring. The first two are mainline proposals and the final two are the in-state pipeline proposals.
TransCanada Alaska, the State’s AGIA licensee, has not entered the pre-filing process with FERC. Until they do, they have asked the OFC to help them coordinate their engagement of the U.S. federal agencies regarding the project. TransCanada Alaska has filed a Right-of-Way application with the DOI Bureau of Land Management. They are undertaking preliminary feasibility and routing studies in preparation for the design of a future gas transmission pipeline. TransCanada Alaska intends to complete its Open Season in July 2010 and anticipates that its application to FERC will be deemed complete in October 2012. I believe it is important to note that the State AGIA license does not grant an exclusive right to land use and right-of-way permits at the State level. Nor is there an exclusive right at the federal level.

Denali—The Alaska Gas Pipeline, is a joint venture of ConocoPhillips and BP. They opted not to engage in the State’s AGIA process. Instead, they have developed a competing project. Denali has entered the formal pre-file application process with FERC and they have filed a Right-of-Way application with the DOI Bureau of Land Management. In December, they submitted a detailed “Field Study Plan” to the FERC docket. The plan includes a resource data gap analysis that examined the public and private information that was produced over the past ten years and provided information regarding Denali’s ongoing and future collection of environmental and cultural resource data. Denali intends to begin its Open Season in 2010.

Now on to the in-state lines. The Alaska Natural Gas Development Authority, has proposed a spurline from Southcentral to Fairbanks. The scoping meetings for this project were just completed. The Army Corps of Engineers is the lead on ANGDA’s federal EIS. The BLM is a cooperating agency while other federal agencies are expected to be participating agencies. ANGDA anticipates their Draft EIS to be issued in December 2009 with a Final EIS in June 2010. Their goal is to have a ROD issued by the end of July 2010.
Enstar has proposed a bulletline that would run from the Gubik Fields near the Brooks Range through Fairbanks to Southcentral. The Army Corps of Engineers will also be the lead on the Enstar EIS. They are discussing potential route options with various federal and state agencies including one option that would run 7 miles along the edge of Denali National Park. Enstar intends to perform field work this summer with crews collecting and analyzing data with respect to water body crossings, seismic zones, wetland delineation, biologic, historical/cultural resources and geotechnical issues. CLICK

SLIDE 6: Obama Administration
The longest ever Presidential election is finally over and federal agencies are deep into the transition phase. Several months before election day, the agencies began to prepare for the transition teams.
I am pleased to report that the Obama administration recognizes the need for an Alaska natural gas pipeline. The President recognizes that the pipeline can increase America’s energy security, create jobs, and help bring clean natural gas to domestic U.S. markets. He has mentioned the project several times since taking office.
I am focusing my attention as Federal Coordinator on briefing key politicals on the project and the work the federal agencies and project proponents have done to date to prepare to build a pipeline that will supply natural gas to the lower 48 and create thousands of new jobs. (Click)


SLIDE 7: What is the Role of the OFC
My job as Federal Coordinator is to ensure coordination, compliance and oversight, as well as information dissemination. We are headquartered in D.C. and as I mentioned earlier, opened our Alaska field office last month. Additional staff will be added as appropriate.
Coordination among the various federal and State agencies is critical to the successful and expeditious construction of an Alaska natural gas transportation project. The OFC is the lead on development of project implementation plans to facilitate the roles of the federal agencies participating in the pipeline effort. The OFC has also begun negotiations with the State of Alaska on a joint Monitoring and Surveillance Agreement to oversee final design and construction of the project.
Expedience is crucial to the success of the project. Delays and unwarranted stipulations will add costs to the project and could result in its being uneconomic.

The OFC will conduct compliance and oversight reviews to ensure that no federal agency attaches any term or condition not required by law that may impair or prevent progress of the projects. We are mindful, of course, of our responsibility to ensure the pipeline is constructed in an environmentally responsible manner.
Given the magnitude of the project it is essential to our collective the success that coordination, oversight and communications are effective and efficient.
The Alaska gasline project is so big, it will make its own weather! CLICK
SLIDE 8: What are the Challenges?
So, what are the major challenges?
For the purposes of this talk, I have identified four categories. At the OFC we try to address challenges one by one, but there are inevitably linkages. The most straightforward but not necessarily simple of the issues are the technical ones. They are solvable but will require world class technical expertise.
There are also economic issues: The project will utilize approximately 2.5 million tons of steel and a 2004 estimate had the project creating 54 million man hours of work. At the same time the $26+ billion cost of the project will need to be financeable by the middle of the next decade and the tariffs have to be low enough to attract shippers.
But the most interesting—and by that I mean challenging—issues are the political and process issues that surround the project. CLICK
SLIDE 9: Technical
I want to talk for a few moments about the technical challenges. These are the straightforward, relatively easy to address issues that science and lots of money are expected to be able to solve. CLICK
SLIDE 10: Technical: Construction in Permafrost
Much of the land along the pipeline route in Alaska is permafrost. It is continuous in the North, discontinuous in the mid-sections and leads to areas near the 60th parallel that are subjected to only seasonal freezing. But even that freezing and thawing can cause the land to shift dramatically placing major stresses on a buried, chilled pipe.
Over the past 30 years, laboratory and field studies carried out by Canadian, American and Russian researchers have illustrated the magnitude of deformations that gas pipelines in permafrost regions undergo when exposed to both freezing and thawing of soils and to the movement of water within permafrost-affected sediments. These have special significance for design, construction and operation of pipelines in cold regions. In fact there are recent reports conducted in Russia that show that frost heave and buckling of pipelines are major causes of natural gas pipeline failures in permafrost regions.
The geologic instability of routes through permafrost put challenging demands on those who design and construct pipelines in cold regions. We have to get it right—the first time. CLICK
SLIDE 11: Technical: Arctic Construction
The second major technical issue involves the difficulty of construction in the Arctic. It is difficult to protect the labor force when it’s 60 below zero or when they are working in very remote locations. CLICK

SLIDE 12: Technical: High Pressure/Large Diameter
This will be the largest high pressure gas pipeline ever built in the Arctic. At this time the expected design will use 48” pipe, X80 steel and 2500/2600 PSIG. The Pipeline Hazardous Materials and Safety Administration, PHMSA, and the Canadian National Energy Board will harmonize requirements on both sides of the border to withstand the extreme Arctic conditions.
SLIDE 13: Technical: Pipeline Design
The last thing we want is for a frost heave to damage the natural gas pipeline. PHMSA is well aware that the presence of permafrost presents significant challenges to the design teams. Their safety review of the natural gas pipeline design will include a detailed analysis which will review the stress based upon operating pressures; the stress due to overburden loading from the permafrost and soil; the operating temperatures of the pipeline; any possible freeze and thaw stresses caused by frost jacking or thaw settlement; and buoyancy control stresses in areas where wetlands thaw.

PHMSA recognizes that continuous or periodic monitoring may be required to confirm compliance with the design. The technical design basis review by PHMSA will be used to ensure that the pipeline owner/operators are considering all criteria in the safety design, construction and ongoing operation of the pipeline. CLICK
SLIDES 14 TO 29: Permafrost Map Slide Show
The climate in the Arctic is changing. It is important that we understand permafrost changes and other effects climate change may have on the pipeline after its construction.
Permafrost trends must be incorporated into the design of a pipeline so it will last 30-50 years. We assume that areas of solid permafrost will be displaced by discontinuous permafrost as change progresses. The University of Alaska, State of Alaska Geophysical Surveys, and U.S. Geological Survey have been working together to map and model the change. On the screen is a model that demonstrates the range of permafrost in Alaska from 1950 to today and how it is forecast to shift by 2100.

The areas in red are permafrost free and as you look further north the colors shift to light blue and dark blue areas – the darker the blue, the colder the ground temperature. Watch what is forecast to happen. CLICK
(PAUSE while slide show runs)
SLIDES 30 TO 40: Permafrost Maps One More Time – 2000-2050
I am going to play the map one more time showing you the map from 2000 to 2050. This time, we look at the forecast change every 5 years. CLICK
(PAUSE while slide show runs)
CLICK
SLIDE 41: Technical: Seismic
On average, Alaska records 50 to 100 earthquakes per day; one magnitude-7 event every year; and a magnitude-8 or larger event every 13 years. The seismicity along the route poses significant challenges to the construction of a natural gas pipeline. Most Alaskans felt the Denali Fault Line magnitude-7.9 earthquake that occurred on November 3, 2002.

That Fault slipped approximately 18 feet laterally and more than 3 feet vertically beneath the Trans-Alaska Pipeline. Not one drop of oil spilled from the pipeline. Why? Because 40 years ago the very best technical experts designed and located TAPS.
Innovative geological and geophysical engineering will be necessary to design a gas pipeline that crosses active faults and fails “safe”. The latest work by the State of Alaska Department of Geological and Geophysical Surveys indicates substantial recent activity along the highway route. Again, we have to get it right, the first time. CLICK
SLIDE 42: Economic
The economic challenges are of a grand scale. We have identified five major economic challenges for this project. CLICK
SLIDE 43: Economic -- Financing a $26+ Billion Enterprise
First, who is expected to finance the largest and most innovative natural gas transportation system ever constructed? Congress authorized a loan guarantee of up to $18 billion in 2004 dollars that will be adjusted for inflation. The loan guarantee is likely to be an essential piece of the financial puzzle. CLICK
SLIDE 44: Economic -- Infrastructure
Second, in order to construct a pipeline, it is imperative to have the necessary infrastructure in place to stage all the manpower and materials for construction. In both the U.S. and Canada, we need to either upgrade or build new bridges, highways, airports, material sites and maintenance camps to support tens of thousands of workers, the heavy equipment and the 2.5 million tons of steel needed to construct the pipeline. The latest estimate outlines at least a $1 Billion in projects just in Alaska. The State of Alaska may utilize part of its Stimulus package funding to begin these critical upgrades this year.
It will take 4-6 years to complete the major infrastructure projects necessary to the project. They must be done before pipeline construction can begin. We can’t afford unnecessary delays in completing these upgrades; they will kill this pipeline project. CLICK
SLIDE 45: Economic – Steel
Third, the project calls for a lot of steel. In ANGPA, Congress expressed the preference that such steel be sourced in North America. Are North American steel producers prepared to deliver 2.5 million tons of high strength steel pipe? CLICK
SLIDE 46: Economic -- Training/Retaining Qualified Labor
The fourth economic challenge is finding and training the labor pool needed on both sides of the border. This pipeline will require more than 50 million man hours of mostly skilled labor. That workforce must be trained and then retained throughout the preconstruction and construction. CLICK
SLIDE 47: Economic -- Natural Gas Prices
It happened in the 1970’s and 1980’s. The price of natural gas plunged. And the pipeline was put on the shelf. Why? Natural gas was discovered in large quantities throughout Canada and in the lower 48; and four LNG import facilities were constructed in the U.S and provided the adequate supply to meet increased demand. Therefore, it was considered that the Alaska pipeline was not really needed.
There has been a lot of talk lately about the economics of a project. Talking about whether or not there still is a market for Alaska natural gas.

I was very pleased to see the comments last week by ConocoPhillips’ President and CEO Jim Mulva regarding the projects economics. He discussed the fact that current gas prices have led ConocoPhillips to cut back on its Canadian operations, but discounted the low prices as a roadblock to the pipeline project's development. He said, "You can't look at gas prices today. You have to look at prices 10 years from now." This is a very important point. Prices are in flux and there are many factors that can change them every day – some natural, others manmade.
When discussing the supply of natural gas for consumption in United States today, the general focal point includes pipeline imports from Canada; imports from overseas in the form of liquefied natural gas (LNG); and domestic production of non-conventional (supplemental sources of supply) natural gas. Based on recent historical analysis and future projections, the Alaska natural gas pipeline would be completed in 2018 and the economics continue to be favorable. Once the pipeline is in service, Alaska’s total natural gas production would be 2.0 trillion cubic feet in 2021 and remains at that level through 2030.
Declining production in Canada is expected to reduce the availability of natural gas supplies for export to the United States. Canada is already experiencing a decline in conventional production from the Western Canadian Sedimentary Basin. Decreased availability of natural gas from the U.S. remains true even if Canada’s Mackenzie Gasline is constructed. The Mackenzie Delta has less than 1 tcf of proven reserves, it’s expected to be easily absorbed in the North American integrated markets without displacing Alaska gas.
The Department of Energy has significantly reduced the short and long term prospects of supply on overseas importation of LNG. Indeed, supply from the international LNG market is dictated by price. In 2007, the United States imported the largest amount LNG ever. However, importation of LNG significantly slowed in the latter part of the year due to increased demand in Europe and Japan. We expect the European nations to consistently outbid the U.S. in the LNG market.

In 2008 the United States imported less than half of LNG that it imported in 2007. Europe and Pacific Rim countries (including Japan) outbid the United States and there was an increase in domestic shale production. It is also worth noting that Europe is likely to expand its LNG import capabilities as a result of the recent Russo-Ukrainian dispute, during which European countries experienced a supply disruption.
The other potential source of natural gas is unconventional domestic production. Shale formations have emerged as a leading source of supply. Domestic natural gas production saw an upward swing beginning in 2006 that generated 3% growth between first-quarter 2006 and first-quarter 2007, followed by an exceptionally large 9% increase between first-quarter 2007 and first-quarter 2008.
The increased domestic natural gas production can be directly related to advances in technology that have allowed more production of shale gas.

The most commonly referred to sources of shale gas production include the Barnett Shale in Texas; the Fayetteville Shale in Arkansas; and the Haynesville Shale in Louisiana. There is one other shale basin that is in its infancy stage of development known as the Marcellus Shale that spans parts of New York, Pennsylvania, Ohio, West Virginia and Kentucky. It is estimated that the Marcellus Shale basin may contain between 50 tcf and 363 tcf of recoverable shale gas.
However, it is important to note that there are many hurdles to overcome in order to effectively produce shale gas. For instance, to produce one well in the Marcellus shale region requires more than one million gallons of fresh water. There is an inadequate amount of waste water treatment facilities with which to handle the refuse derived from hydofracing the wells. There are environmental concerns relating to noise, heavy truck traffic, air pollution and the chemical solution utilized in hydofracing. These are affecting shale gas projects today. For example, New York has slowed down shale production until the state can develop appropriate regulations. Lastly, much of the basin is located below private property where lease negotiations are becoming ever more cumbersome. CLICK
SLIDE 48: Politics!
The technical and economic challenges are intriguing but there are bigger challenges. Politics are at play! CLICK
SLIDE 49: The Competitors
I’m pretty sure Congress didn’t envision the competitive process that has evolved. The good news is that both Denali and TransCanada Alaska are excellent candidates and bring unique strengths to the project. The competition has spurred fast moving developments. Only one pipeline will be built. So the key question remains, will the two competitors merge? And when? The competition will become inefficient and costly at some point in the near future. Federal agencies are prepared to deal with both projects for as long as necessary but it is not an ideal situation and it certainly isn’t efficient. CLICK

SLIDE 50: Key Players
The next interesting piece of the puzzle is how the U.S. and Canadian federal governments and the State of Alaska and provincial and territorial governments—who want to see this pipeline built—ensure it happens. Will the Governor or the President or the Prime Minister step in to break the gridlock and take control similar to the 1970’s process? Will Congress act? And, with Governor Palin in cycle, how will Alaska State politics affect the State’s actions? Inevitably, there will be local winners and losers as ports of entry and final routes are chosen. How will local and regional politics – always so lively in both Alaska and Western Canada – affect the project? CLICK
SLIDE 51: Process Related Issues
The final challenges we will encounter are process related, permitting, environmental review and consultations. CLICK
SLIDE 52: Process Related Issues: U.S. Federal Agencies
On our side there are at least 22 federal agencies that have a role to play. Just keeping track of these agencies and their responsibilities is a full-time job. CLICK
SLIDE 53: Process Related Issues: Enviro Review
The State of Alaska and the Government of Canada also have approval processes that must proceed alongside FERC licensing.
Many of you are familiar with the FERC process. ANGPA designates the FERC as the lead agency for completing the environmental review, or EIS, and gives them 18 months to do it. That timeline puts the Alaska project into a different category at FERC. The Government of Canada and the State of Alaska have agreed to time their processes to coincide with that aggressive schedule. The schedule is very demanding, especially if two applications move to the EIS phase of the project. CLICK
SLIDE 54: FERC Pre-Filing Enviro Review Process
On this slide, the check depicts the point at which Denali and TransCanada Alaska’s latest timelines are expected to mesh. The boxes above the check indicate activities each expect to complete within the next 24 months. (NOTE the public input opportunities, comment periods.) A major part of the FERC pre-filing process is completion of the FERC Resource Reports. CLICK

SLIDE 55: Process -- FERC Resource Reports
The Environmental Resource Reports constitute the “environmental report” portion of a FERC application and are similar to the information required by the Canadian authorities. Both applicants expect to complete Resource Reports one and ten before the end of the year as they prepare their Open Season packages and get ready for EIS Scoping. CLICK
SLIDE 56: Process – Consultations GTG
The last issue I want to discuss is consultation. There are two separate requirements. First, when the federal government permits a project that will impact Native Americans we are required to engage in Government-to-Governments (tribal) stakeholder consultations with all directly or indirectly affected federally recognized tribes.
These consultations are crucial. They provide the forum to ensure that the impacted Alaska Natives’ concerns are considered as the planning moves forward. In order to ensure continuity throughout the life of the project, FERC is working to establish a written Government-to-Government consultation plan that will serve the needs of all the federal agencies. The OFC will provide oversight to ensure the plan is followed. CLICK
SLIDE 57: Process – Consultations Section 106
The second federal agency requirement is a cultural and historic resource analysis and consultation. The National Historic Preservation Act of 1966 created the National Register of Historic Places and the Section 106 review process. The Section 106 consultation ensures that preservation values for cultural and historic properties are factored into federal agency planning and decisions. FERC is the lead federal agency for the Section 106 review. CLICK
LAST SLIDE: 58
Challenges? We have many. Insurmountable? Not if we all pledge to come to the table with an attitude that we want to find ways to say “yes”. North America needs this gas. Alaska and Western Canada need this project. Its time is now! Thank you. THE END

It is important for the RDC to continue spreading the message that exploration is essential. We still need to find 15 tcf more of natural gas to make this project economic. That won’t happen if companies don’t explore. The OCS, NPRA, ANWR are all places that could potentially bring us those critical extra tcf of gas. We all need to work together to educate the appropriate policy makers to ensure Alaska is a place companies can develop.

Attachments: 

Alaska’s Natural Gas Pipeline: Closer to Reality?

Release Date: 
03/11/2009

 

Alaska Natural Gas Pipeline: Closer to Reality?
5th Annual Pipeline Opportunities Conference
Houston, TX
March 11, 2009

By Drue Pearce, Federal Coordinator
Office of the Federal Coordinator
Alaska Natural Gas Transportation Projects

SLIDE 1: Introduction Page
Good Afternoon—It’s nice to be back in Houston. I want to take this opportunity to thank the Pipeline and Gas Journal for inviting me back to the Pipeline Opportunities Conference. I’m the first of the four Alaska-centric speakers. I’m here today to tell you about the need for and challenges of getting Alaska’s North Slope natural gas to market.
One of the largest known reserves of natural gas in America sits in Alaska’s Arctic, associated with the development of oil at Prudhoe Bay. The 35 trillion cubic feet of proven natural gas reserves will make a significant long-term contribution to the United States’ energy supplies. Since the late 1990’s, the State of Alaska, the three North Slope Producers, TransCanada, and other major pipeline companies have been pondering whether now is the time when construction of the gasline is economically feasible. CLICK

SLIDE 2: Pipeline Projects
Alaska has a unique pipeline history. After discovery of the elephant sized Prudhoe Bay field in 1967, the nation’s largest oil pipeline was built. A parallel gasline has remained a dream. CLICK

SLIDE 3: TAPS
In the early 1970’s the Trans Alaska Pipeline System, known as TAPS, was built to transport oil from Prudhoe Bay to the port of Valdez. There were countless environmental, arctic construction, and native subsistence and sovereignty challenges to be resolved before TAPS could be built. It took federal enactment of the Alaska Native Claims Settlement Act and the Trans Alaska Pipeline Authorization Act in order for construction to proceed. At the time, the necessary infrastructure did not exist. It all had to be built before pipeline construction could commence.
We face a host of new challenges with this project—a mostly buried, chilled, high pressure gas pipeline. CLICK

SLIDE 4: ANGTA
While TAPS was being constructed, plans were initiated to build a large diameter pipeline to deliver the associated natural gas to the lower 48. Congress enacted the Alaska Natural Gas Transportation Act and President Carter designated the route, design and project sponsors for this transportation system. The southern portions of the pipeline shown in light green on this map are known as the “pre-build” and went into operation in 1981-1982. The northern portion shown in dark green, would link North Slope gas to the pre-built legs. Foothills Pipe Line Ltd, now a subsidiary of TransCanada, is the legacy owner and operator of the pre-build. The northern portion is the route of the pipeline that has remained an elusive target but irresistible dream to Alaskans. CLICK


SLIDE 5: ANGPA
There have been countless proposals to produce North Slope gas since the late 1970’s. The latest effort led to Congress passing the Alaska Natural Gas Pipeline Act, known as ANGPA in 2004. That statute created my office, the Office of the Federal Coordinator for Alaska Natural Gas Transportation Projects, and encouraged the expeditious approval, construction, and operation of a natural gas transportation project for delivery of North Slope gas to U.S. markets.

SLIDE 6: Planned Pipeline Projects
There are 4 projects that the Office of the Federal Coordinator is monitoring. The first two are mainline proposals and the final two are bullet/spurline proposals.
TransCanada Alaska has begun engagement of the U.S. federal agencies regarding their project. Since you will hear from them, I won’t repeat the messages you will hear from the State of Alaska and TransCanada. It is important to note however, that the State AGIA license does not grant an exclusive right to land use and right-of-way permits at the State level. Nor is there an exclusive right at the federal level.
Denali is a joint venture of ConocoPhillips and BP. They developed a competing project that does not comply with all of the State of Alaska’s requirements – which the Governor calls the “must haves”. Denali has entered the formal pre-file application process with the FERC and they have filed a Right-of-Way application with BLM. Both these proposals follow essentially the same route as contemplated by President Carter in 1977.
You will also hear from the Alaska Natural Gasline Development Authority, known as ANGDA. They have proposed a spurline from Southcentral to Fairbanks. The Army Corps of Engineers is lead on their EIS. And, they have just completed their scoping meetings.
Enstar, SouthCentral Alaska’s gas distribution company, has proposed a bulletline that would run from the Brooks Range through Fairbanks to Southcentral. The Army Corps of Engineers will also be the lead on their EIS. They are discussing potential route options with various federal and state agencies including one option that would run 7 miles along the edge of Denali National Park. (Click)

SLIDE 7: Obama Administration
The longest ever Presidential election is finally over and federal agencies are deep into the transition phase. Several months before election day, the agencies began to prepare for the transition teams.
I am pleased to report that the Obama administration recognizes the need for an Alaska natural gas pipeline. The President recognizes that the pipeline can increase America’s energy security, create jobs, and help bring clean natural gas to domestic U.S. markets. He has mentioned the project several times since taking office.
I am focusing my attention as Federal Coordinator on briefing key politicals on the project and the work the federal agencies and project proponents have done to date to prepare to build a pipeline that will supply natural gas to the lower 48 and create thousands of new jobs. (Click)

SLIDE 8: What is the Role of the OFC
My job as Federal Coordinator is to ensure coordination, compliance and oversight, as well as information dissemination. We are headquartered in D.C. and opened our Alaska field office last month with an Environmental Engineer on staff. Additional staff will be added as appropriate.
Coordination among the various federal and State agencies is critical to the successful and expeditious construction of an Alaska natural gas transportation project. The OFC is the lead on development of project implementation plans to facilitate the roles of the federal agencies participating in the pipeline effort. The OFC has also begun negotiations with the State of Alaska on a joint Monitoring and Surveillance Agreement to oversee final design and construction of the project.
Expedience is crucial to the success of the project. The OFC will conduct compliance and oversight reviews to ensure that no federal agency attaches any term or condition not required by law that may impair or prevent progress of the projects.
Given the magnitude of the project it is essential to the success of the project that coordination, oversight and communications are effective and efficient.
The Alaska gasline project is so big, it will make its own weather! CLICK

SLIDE 9: What are the Challenges?
So, what are the major challenges?
For the purposes of this talk, I have identified four categories. At the OFC we try to address challenges one by one, but there are inevitably linkages. The most straightforward but not necessarily simple of the issues are the technical ones. They are solvable but will require world class technical expertise.
There are also economic issues: The project will utilize approximately 2.5 million tons of steel and a 2004 estimate had the project creating 54 million man hours of work. At the same time the $26+ billion cost of the project will need to be financeable by the middle of the next decade and the tariffs have to be low enough to attract shippers.
But the most interesting—and by that I mean challenging—issues are the political and process issues that surround the project. CLICK

SLIDE 10: Technical
I want to talk for a few moments about the technical challenges. These are the straightforward, relatively easy to address issues that science and lots of money are expected to be able to solve. CLICK

SLIDE 11: Technical: Construction in Permafrost
Much of the land along the pipeline route in Alaska is permafrost. It is continuous in the North, discontinuous in the mid-sections and leads to areas near the 60th parallel that are subjected to only seasonal freezing. But even that freezing and thawing can cause the land to shift dramatically placing major stresses on a buried, chilled pipe.
Over the past 30 years, laboratory and field studies carried out by Canadian, American and Russian researchers have illustrated the magnitude of deformations that gas pipelines in permafrost regions undergo when exposed to both freezing and thawing of soils and to the movement of water within permafrost-affected sediments. These have special significance for design, construction and operation of pipelines in cold regions. In fact there are recent reports conducted in Russia that show that frost heave and buckling of pipelines are major causes of natural gas pipeline failures in permafrost regions.
The geologic instability of routes through permafrost put challenging demands on those who design and construct pipelines in cold regions. We have to get it right—the first time. CLICK

SLIDE 12: Technical: Arctic Construction
The second major technical issue involves the difficulty of construction in the Arctic. It is difficult to protect the labor force when it’s 60 below zero or when they are working in very remote locations. CLICK

SLIDE 13: Technical: High Pressure/Large Diameter
This will be the largest high pressure gas pipeline ever built in the Arctic. At this time the expected design will use 48” pipe, X80 steel and 2500/2600 PSIG. The Pipeline Hazardous Materials and Safety Administration, PHMSA, and the Canadian National Energy Board will harmonize requirements on both sides of the border to withstand the extreme Arctic conditions.

SLIDE 14: Technical: Pipeline Design
The last thing we want is for a frost heave to damage the natural gas pipeline. PHMSA is well aware that the presence of permafrost presents significant challenges to the design teams. Their safety review of the natural gas pipeline design will include a detailed analysis which will review the stress based upon operating pressures; the stress due to overburden loading from the permafrost and soil; the operating temperatures of the pipeline; any possible freeze and thaw stresses caused by frost jacking or thaw settlement; and buoyancy control stresses in areas where wetlands thaw.
PHMSA recognizes that continuous or periodic monitoring may be required to confirm compliance with the design. The technical design basis review by PHMSA will be used to ensure that the pipeline owner/operators are considering all criteria in the safety design, construction and ongoing operation of the pipeline. CLICK

SLIDES 15 TO 30: Permafrost Map Slide Show
The climate in the Arctic is changing. It is important that we understand permafrost changes and other effects climate change may have on the pipeline after its construction.
Permafrost trends must be incorporated into the design of a pipeline so it will last 30-50 years. We assume that areas of solid permafrost will be displaced by discontinuous permafrost as change progresses. The University of Alaska, State of Alaska Geophysical Surveys, and U.S. Geological Survey have been working together to map and model the change. On the screen is a model that demonstrates the range of permafrost in Alaska from 1950 to today and how it is forecast to shift by 2100. The areas in red are permafrost free and as you look further north the colors shift to light blue and dark blue areas – the darker the blue, the colder the ground temperature. Watch what is forecast to happen. CLICK
(PAUSE while slide show runs)

SLIDES 31 TO 41: Permafrost Map Slide Show One More Time – 2000-2050
I am going to play the map one more time showing you the map from 2000 to 2050. This time, we look at the forecast change every 5 years. CLICK
(PAUSE while slide show runs)
CLICK

SLIDE 42: Technical: Seismic
On average, Alaska records 50 to 100 earthquakes per day; one magnitude-7 event every year; and a magnitude-8 or larger event every 13 years. The seismicity along the route poses significant challenges to the construction of a natural gas pipeline. Most Alaskans felt the Denali Fault Line magnitude-7.9 earthquake that occurred on November 3, 2002. That Fault slipped approximately 18 feet laterally and more than 3 feet vertically beneath the Trans-Alaska Pipeline. Not one drop of oil spilled from the pipeline. Why? Because 40 years ago the very best technical experts designed and located TAPS.
Innovative geological and geophysical engineering will be necessary to design a gas pipeline that crosses active faults and fails “safe”. The latest work by the State of Alaska Department of Geological and Geophysical Surveys indicates substantial recent activity along the highway route. Again, we have to get it right, the first time. CLICK

SLIDE 43: Economic
The economic challenges are of a grand scale. We have identified five major economic challenges for this project. CLICK

SLIDE 44: Economic -- Financing a $26+ Billion Enterprise
First, who is expected to finance the largest and most innovative natural gas transportation system ever constructed? Congress authorized a loan guarantee of up to $18 billion in 2004 dollars that will be adjusted for inflation. The loan guarantee is likely to be an essential piece of the financial puzzle. CLICK

SLIDE 45: Economic -- Infrastructure
Second, in order to construct a pipeline, it is imperative to have the necessary infrastructure in place to stage all the manpower and materials for construction. In both the U.S. and Canada, we need to either upgrade or build new bridges, highways, airports, material sites and maintenance camps to support tens of thousands of workers, the heavy equipment and the 2.5 million tons of steel needed to construct the pipeline. The latest estimate outlines at least $1 Billion in projects just in Alaska. The State of Alaska may utilize part of its Stimulus package funding to begin these critical upgrades this year.
It will take 4-6 years to complete the major infrastructure projects necessary to the pipeline project. They must be done before pipeline construction can begin. We can’t afford unnecessary delays in completing these upgrades; they will kill this pipeline project. CLICK

SLIDE 46: Economic – Steel
Third, the project calls for a lot of steel. In ANGPA, Congress expressed the preference that such steel be sourced in North America. Are North American steel producers prepared to deliver 2.5 million tons of high strength steel pipe? CLICK

SLIDE 47: Economic -- Training/Retaining Qualified Labor
The fourth economic challenge is finding and training the labor pool needed on both sides of the border. This pipeline will require more than 50 million man hours of mostly skilled labor. That workforce must be trained and then retained throughout the preconstruction and construction. CLICK

SLIDE 48: Economic -- Natural Gas Prices
It’s happened to this dream before. The price of natural gas plunges. And the Alaska dream goes back on the shelf. Dr. Myers is going to discuss markets in more depth.
When discussing the supply of natural gas for consumption in United States, generally the focal point includes pipeline imports from Canada; imports of LNG; and domestic production of non-conventional (supplemental sources of supply) natural gas. Based on recent historical analysis and future projections, the Alaska natural gas pipeline would be completed in 2020 and the economics continue to be favorable. The EIA 2008 International Energy Outlook expected the “rising natural gas prices to provide sufficient incentive for an Alaska natural gas pipeline.”
With respect to Canada, declining conventional production in Western Canada is expected to reduce the availability of natural gas supplies for export to the United States.
Regarding the reliance on overseas importation of LNG, the Department of Energy has significantly reduced the short and long term prospects of supply. Indeed, supply from the international LNG market is dictated by price.
In 2008 the United States imported less than half of LNG that it imported in 2007. Europe and Pacific Rim countries (including Japan) outbid the United States and there was an increase in domestic shale production. It is also worth noting that Europe is likely to expand its LNG import capabilities as a result of the recent Russo-Ukrainian dispute, during which European countries experienced a supply disruption.
With respect to unconventional domestic production of natural gas, shale formations have emerged as a leading source of supply. While shale gas production is likely to continue to increase, there are some disadvantages to shale gas production. You heard the discussions earlier – the need for massive amounts of water is a limiting factor as is the variable gas quality. CLICK

SLIDE 49: Politics!
The technical and economic challenges are intriguing but there are bigger challenges. Politics are at play! CLICK

SLIDE 50: The Competitors
I’m pretty sure Congress didn’t envision the competitive process that has evolved. The good news is that both Denali and TransCanada Alaska are excellent candidates and bring unique strengths to the project. The competition has spurred fast moving developments. Only one pipeline will be built. So the key question remains, will the two competitors merge? And when? The competition will become inefficient and costly at some point in the near future. Federal agencies are prepared to deal with both projects for as long as necessary but it is not an ideal situation and it certainly isn’t efficient. CLICK

SLIDE 51: Key Players
The next interesting piece of the puzzle is how the U.S. and Canadian federal governments and the State of Alaska and provincial and territorial governments—who want to see this pipeline built—ensure it happens. Will the Governor or the President or the Prime Minister step in to break the gridlock and take control similar to the 1970’s process? Will Congress act? And, with Governor Palin in cycle, how will Alaska State politics affect the State’s actions? Inevitably, there will be local winners and losers as ports of entry and final routes are chosen. How will local and regional politics – always so lively in both Alaska and Western Canada – affect the project? CLICK

SLIDE 52: Process Related Issues
The final challenges we will encounter are process related, permitting, environmental review and consultations. CLICK

SLIDE 53: Process Related Issues: U.S. Federal Agencies
On our side there are at least 22 federal agencies that have a role to play. Just keeping track of these agencies and their responsibilities is a full-time job. CLICK

SLIDE 54: Process Related Issues: Enviro Review
The State of Alaska and the Government of Canada also have approval processes that must proceed alongside FERC licensing.
Many of you are familiar with the FERC process. ANGPA designates the FERC as the lead agency for completing the environmental review, or EIS, and gives them 18 months to do it. That timeline puts the Alaska project into a different category at FERC. The Government of Canada and the State of Alaska have agreed to time their processes to coincide with that aggressive schedule. The schedule is very demanding, especially if two applications move to the EIS phase of the project. CLICK

SLIDE 55: FERC Pre-Filing Enviro Review Process
On this slide, the check depicts the point at which Denali and TransCanada Alaska’s latest timelines are expected to mesh. The boxes above the check indicate activities each expect to complete within the next 24 months. (NOTE the public input opportunities, comment periods.) A major part of the FERC pre-filing process is completion of the FERC Resource Reports. CLICK

SLIDE 56: Process -- FERC Resource Reports
The Environmental Resource Reports constitute the “environmental report” portion of a FERC application and are similar to the information required by the Canadian authorities. Both applicants expect to complete Resource Reports one and ten before the end of the year as they prepare their Open Season packages and get ready for EIS Scoping. CLICK

SLIDE 57: Process – Consultations GTG
The last issue I want to discuss is consultation. There are two separate requirements. First, when the federal government permits a project that will impact Native Americans we are required to engage in Government-to-Governments (tribal) stakeholder consultations with all directly or indirectly affected federally recognized tribes.
These consultations are crucial. They provide the forum to ensure that the impacted Alaska Natives’ concerns are considered as the planning moves forward. In order to ensure continuity throughout the life of the project, FERC is working to establish a written Government-to-Government consultation plan that will serve the needs of all the federal agencies. The OFC will provide oversight to ensure the plan is followed. I understand how important it is to listen to and work with the impacted residents, especially Alaska Natives and First Nations, as they express their concerns about projects. I’ve already begun a dialogue and will, next week begin a dialogue at the Tanana Chiefs Conference Annual Convention in Fairbanks about the consultation process. CLICK

SLIDE 58: Process – Consultations Section 106
Federal agencies are also required to do a cultural and historic resource analysis and consultation. The National Historic Preservation Act of 1966 created the National Register of Historic Places and the Section 106 review process. The Section 106 consultation ensures that preservation values for cultural and historic properties are factored into federal agency planning and decisions. FERC is the lead federal agency for the Section 106 review. CLICK

LAST SLIDE: 59
Challenges? We have many. Insurmountable? Not if we all pledge to come to the table with an attitude that we want to find ways to say “yes”. North America needs this gas. Alaska and Western Canada need this project. Its time is now! Thank you again for inviting me back to the Arctic Gas Symposium.
THE END

Attachments: 

Update on the Alaska Natural Gas Transportation Projects

Release Date: 
12/10/2009

UPDATE ON FEDERAL ACTIVITIES TOWARD COORDINATING THE
ALASKA NATURAL GAS TRANSPORTATION PROJECTS

Presented to the DOT Pipeline Hazardous Materials & Safety Administration Advisory Council Meeting
Alexandria, VA
December 10, 2010

by Drue Pearce
Federal Coordinator,
Alaska Natural Gas Transportation Projects


SLIDE 1 – COVER SLIDE
LET ME BEGIN TODAY BY SAYING THE COMMERCIALIZATION OF NORTH SLOPE NATURAL GAS IS CRITICAL, AND NOT JUST FOR ALASKA. AT A RECENT DEVELOPMENT CONFERENCE IN ALASKA, DAVID HOLT, PRESIDENT OF THE CONSUMER ENERGY ALLIANCE, SAID ALL ROADS THAT LEAD TO ENERGY SECURITY FOR AMERICA RUN THROUGH ALASKA, AND I TRULY BELIEVE THAT’S THE CASE, NOT ONLY BECAUSE IT’S THE MISSION OF THE OFC – TO ADVANCE OUR NATION’S ENERGY AND ECONOMIC SECURITY BY EXPEDITING THE DELIVERY OF CLEAN NATURAL GAS FROM THE NORTH SLOPE OF ALASKA TO NORTH AMERICAN MARKETS — BUT BECAUSE CONGRESS AND A SUCCESSION OF PRESIDENTS HAVE RECOGNIZED THIS SAME PERSPECTIVE.
THEY’VE ALSO RECOGNIZED A VERY DISTINCT NEED FOR AN OFFICE TO COORDINATE THE FEDERAL PROCESS OF LICENSING, PERMITTING AND OVERSIGHT OF DESIGN AND CONSTRUCTION OF THE GAS PIPELINE PROJECT.
FOR THAT REASON, THE OFC WAS CREATED IN 2004 AND GIVEN THE AUTHORITIES OF THE CARTER/REAGAN ERA FEDERAL INSPECTOR. I WAS SWORN IN 36 MONTHS AGO, AND IN THAT TIME THE OFFICE HAS BEEN DEDICATED TO A SINGLE MISSION – TO GET THIS PIPELINE BUILT. THE OFC COORDINATES AND EXPEDITES THE WORK OF 24 PLUS FEDERAL AGENCIES WITH ROLES IN THE PERMITTING, LICENSING, CERTIFICATING THE NATURAL GAS PIPELINE -- I THINK OF THE OFC AS BEING TASKED WITH DOING THE JOB THAT COMBINES THE TALENTS OF TRAFFIC COP, DIPLOMAT, PSYCHIC, OMBUDSMAN, ANALIST AND ENGINEER.
IN ADDITION TO THE US FEDERAL COORDINATION, WE WORK WITH THE CANADIAN GOVERNMENT, THE STATE OF ALASKA AND ALL STAKEHOLDERS… FROM ALASKA NATIVE TRIBES TO THE CONSERVATION COMMUNITY TO THE UNIONS.
FOR PURPOSES OF THIS PRESENTATION, I WANT TO TOUCH ON THE MOST RELAVANT OF OUR MAJOR EFFORTS. FIRST ALLOW ME TO GIVE YOU SOME BACKGROUND SOME GENERAL INFORMATION ABOUT BOTH PROJECT APPLICANTS AND THE OPEN SEASON PROCESS. CLICK
SLIDE 2 – APPLICANT LOGO SLIDE
THERE ARE TWO APPLICANTS, DENALI (A CONSORTIUM OF BP AND CONOCOPHILLIPS) AND THE ALASKA PIPELINE PROJECT KNOWN AS APP (A PARTNERSHIP OF TRANSCANADA AND EXXONMOBIL). BOTH HAVE ENTERED FERC’S PRE-FILE PROCESS AND ARE WORKING ON THEIR FERC OPEN SEASON PACKAGES. THE APP WILL SUBMIT ITS OPEN SEASON PACKAGE TO FERC IN JANUARY 2010. DENALI ANTICIPATES SUBMITTING ITS PLAN IN THE FOURTH QUARTER OF NEXT NEAR.
IN THE ENABLING LEGISLATION, CONGRESS INSTRUCTED FERC TO ESTABLISH A NATURAL GAS PIPELINE OPEN SEASON PROCESS SPECIFIC TO THE ALASKA PIPELINE THAT INCLUDES OPPORTUNITIES FOR PUBLIC REVIEW AND COMMENT. ANGPA INSTRUCTED FERC TO ISSUE REGULATIONS TO INCLUDE PROCEDURES FOR THE ALLOCATION OF CAPACITY; CRITERIA FOR AND TIMING OF ANY OPEN SEASON THAT WOULD PROMOTE COMPETITION IN THE EXPLORATION, DEVELOPMENT, AND PRODUCTIONS OF ALASKA NATURAL GAS; AND TO PROVIDE FOR EXPANSION OPEN SEASONS WHICH MUST PROVIDE THE OPPORUTNITY FOR THE TRANSPORTATION OF NATURAL GAS OTHER THAN FROM THE PRUDHOE BAY AND POINT THOMPSON FIELDS. THE FERC ISSUED THEIR FINAL RULE WITH REVISION IN JUNE 2005 AND ESTABLISHED THE FOLLOWING OPEN SEASON PACKAGE PROCESS: CLICK
SLIDE 3 – FERC PROCESS
• THE APPLICANT FILES AN OPEN SEASON PACKAGE WITH THE FERC FOR REVIEW AND APPROVAL;
• THE FILING IMMEDIATELY IS PUBLISHED FOR A 30 DAY THIRD PARTY REVIEW, WHICH ALLOWS FOR PUBLIC COMMENT;
• THE APPLICANT HAS A 15 DAY PERIOD TO RESPOND TO THIRD PARTY COMMENTS; WHICH IS
• FOLLOWED BY A 15-DAY FERC REVIEW AND ACTION BY THE COMMISSION;
• THE APPLICANT FINALIZES THE OPEN SEASON PLAN AND PROVIDES THE OPEN SEASON PACKAGE TO THE PUBLIC; AND
• THEN 30 DAYS LATER, THE APPLICANT COMMENCES THE OPEN SEASON FOR AT LEAST 90 ADDITIONAL DAYS. CLICK
SLIDE 4 – APP PROCESS
THE APP ENTERED THE FERC PRE-FILE PROCESS IN MAY 2009. THEY ARE HOLDING DISCUSSIONS WITH POTENTIAL SHIPPERS IN ALASKA AND CANADA, FOR ROUTES TO THE ALBERTA HUB OR AN LNG OPTION TO VALDEZ, ALASKA. THE APP IS ALSO COMPLETING AN IN-STATE GAS STUDY, REQUIRED BY STATUTE, TO FILE AS PART OF THE OPEN SEASON PACKAGE. THEY ARE THE STATE OF ALASKA’S LICENSEE UNDER THE ALASKA GASLINE INDUCEMENT ACT (AGIA). CLICK
SLIDE 5 – DENALI PROCESS
DENALI, THE SECOND APPLICANT, ENTERED THE FERC PRE-FILE PROCESS IN JUNE 2008. IN MAY 2009, FERC NOTIFIED DENALI THAT THEY HAD SELECTED ARGONNE NATIONAL LABORATORY AS THE THIRD-PARTY CONTRACTOR TO ASSIST FERC STAFF IN THE PREPARATION OF DENALI’S ENVIRONMENTAL IMPACT STATEMENT (EIS). DENALI INDICATES THAT IT WILL BEGIN ITS OPEN SEASON IN LATE 2010. THEY TOO HAVE BEGUN DISCUSSIONS WITH POTENTIAL SHIPPERS. CLICK
SLIDE 6 - CANADA APPLICATION PROCESSES
OUR DIRECTOR OF PERMITS, SCHEDULING AND COMPLIANCE RECENTLY RETURNED FROM OTTAWA WHERE HE PARTICIPATED IN THE STATE DEPARTMENT’S ANNUAL ENERGY CONSULTATIVE MECHANISM (ECM) MEETING WHICH CONSISTS OF A BILATERAL ENERGY TRADE DELEGATION. THE OFC HAS PARTICIPATED, AT THE REQUEST OF THE STATE DEPARTMENT, FOR THE PAST THREE YEARS AT THIS FORUM, WHICH PROVIDES A FORMAT FOR ENERGY AND TRADE EXPERTS FROM THE U.S. AND CANADA TO EXPLORE MUTUAL ISSUES INCLUDING WORLD ENERGY PRICES AND REGULATORY PERMITTING ISSUES. THE TWO DELEGATIONS DISCUSSED THE PROGRESS BEING MADE ON THE DEVELOPMENT OF THE ALASKA GAS PIPELINE PROJECT.
THE ALASKA PIPELINE PROJECT’S APPLICATION RENEWAL IN CANADA WILL BE PROCESSED BY THE NORTHERN PIPELINE AGENCY (NPA). THE NPA WAS CREATED WITH THE PROCLAMATION OF THE NORTHERN PIPELINE ACT IN APRIL 1978 TO OVERSEE PLANNING AND CONSTRUCTION OF THE CANADIAN PORTION OF THE ALASKA HIGHWAY GAS PIPELINE PROJECT BY THE FOOTHILLS GROUP OF COMPANIES. FOOTHILLS IS NOW A SUBSIDEARY OF TRANSCANADA.
THE NPA ACTS AS A SINGLE WINDOW BETWEEN FEDERAL AUTHORITIES AND THE FOOTHILLS GROUP OF COMPANIES, BETWEEN PROVINCIAL AND TERRITORIAL GOVERNMENTS AND THE GOVERNMENT OF THE UNITED STATES. IN KEEPING WITH THE ACT, MANY REGULATORY POWERS OF OTHER FEDERAL CANADAIAN DEPARTMENTS AND AGENCIES RELATED TO THE PIPELINE PROJECT ARE DELEGATED TO THE NPA. THE NATIONAL ENGERY BOARD ALSO HAS A ROLE IN ISSUING A NOTICE TO PROCEED.
THE DENALI APPLICATION IN CANADA WILL BE COORDINATED BY THE MAJOR PROJECTS MANAGEMENT OFFICE (MPMO). THE MPMO WAS ESTABLISHED IN 2007 TO SUPPORT THE GOVERNMENT OF CANADA’S NEW APPROACH TO THE REGULATORY REVIEW OF MAJOR RESOURCE PROJECTS – AN APPROACH THAT ENSURES A MORE EFFECTIVE, ACCOUNTABLE, TRANSPARENT AND TIMELY REVIEW PROCESS.
THE MPMO'S MANDATE IS TO PROVIDE OVERARCHING PROJECT COORDINATION, MANAGEMENT AND ACCOUNTABILITY FOR MAJOR RESOURCE PROJECTS WITHIN THE CONTEXT OF THE EXISTING FEDERAL REGULATORY REVIEW PROCESS AND UNDERTAKE RESEARCH AND IDENTIFY OPTIONS THAT DRIVE FURTHER PERFORMANCE IMPROVEMENTS TO THE FEDERAL REGULATORY SYSTEM FOR MAJOR RESOURCE PROJECTS. DENALI IS REQUIRED TO SUBMIT TO THE MPMO A PROJECT DESCRIPTION AND THEN THE MPMO WILL COORDINATE A PROJECT AGREEMENT BETWEEN THE APPROPRIATE CANADIAN AGENCIES THAT HAVE PERMITTING AND AUTHORIZATION RESPONSIBILITIES. CLICK
SLIDE 7 -- OFC WORK TO DATE
SO WHAT HAS THE OFC BEEN UP TO FOR THE PAST 36 MONTHS? TO SET THE STAGE FOR THE WORK AHEAD, WE FIRST HAD A GAP ANALYSIS PREPARED IN 2007 THAT IDENTIFIED GAPS AND OVERLAPS THAT COULD JEOPARDIZE THE EFFORT TO EXPEDITE CONSTRUCTION. THE GAP ANALYSIS WAS COMMISSIONED TO “PROVIDE UNBIASED STUDIES AND EVALUATIONS OF ENVIRONMENTAL, ENGINEERING, AND REGULATORY ISSUES.” CLICK
SLIDE 8 – OFC
I CHOSE THIS METHODOLOGY IN ORDER TO IDENTIFY THE GAPS IN THE PROCESS AND THEN TO DRAFT AN IMPLEMENTATION PLAN FOR EACH APPLICANT. THESE PLANS WILL PROVIDE AN AGREED UPON ROADMAP FOR EACH TO FOLLOW AS THEY PROGRESS TO FILING THEIR FERC APPLICATIONS. THESE PLANS ALLOW FOR EARLY COORDINATION AND A PROJECT MANAGEMENT APPROACH BASED ON A COMMON UNDERSTANDING AND COMMITMENT TO THE PERMITTING PROCESS. THE IMPLEMENTATION PLANS ALSO ALLOW THE OFC TO MAKE SURE THAT ALL FEDERAL AGENCIES FULLY COMPLY WITH THE FEDERAL LAWS THAT GOVERN THIS UNIQUE PROJECT.
NEXT, WE BEGAN WORK ON A PERMIT MATRIX – AN OVERALL PICTURE OF THE PERMITTING PROCESS – FOR EACH APPLICANT SO THAT ALL AGENCIES, BOTH COMPANIES, AND THE PUBLIC HAVE AN ORGANIZED AND AGREED UPON FRAMEWORK TO USE AS THE AGENCIES PREPARE, REVIEW AND ISSUE PERMITS, LICENSES AND CERTIFICATIONS.
WE’VE ALSO ESTABLISHED A TECHNICAL REVIEW TEAM, CHAIRED BY THE OFC AND COMPRISED OF TECHNICIANS, FEDERAL AND STATE AGENCY EXPERTS AND CANADIAN EXPERTS TO MEET REGULARLY TO ENSURE TECHNICAL ISSUES DO NOT DELAY THIS PROJECT. THE TEAM WILL SHARE ENGINEERING INFORMATION AND EXPERTISE AS THEY IDENTIFY PROJECT TECHNICAL ISSUES SUCH AS PIPELINE, DESIGN, SECURITY, LEAK PREVENTION, BEST AVAILABLE CONTROL TECHNOLOGY, PERMAFROST, SEISMIC STANDARDS, AND EMISSIONS. THEY WILL ALSO IDENTIFY ISSUES THAT REQUIRE EARLY RESOLUTION AND FIND SOLUTIONS BEFORE IMPACTING THE PROJECT TIMELINE. THE TEAM HAS BEGUN MEETING. CLICK
SLIDE 9 -- GIS SYSTEM
THE OFC IS ALSO WORKING ON A PROTOTYPE GEOGRAPHIC INFORMATION SYSTEM OR GIS. FOR YEARS, ALASKANS HAVE DISCUSSED THE NEED FOR BETTER MAPPING AND MANY OF OUR PROJECT AGENCIES IDENTIFIED A NEED FOR A SINGLE REFERENCE SYSTEM FOR DATA AND INFORMATION COLLECTION. THERE IS NOT A CONSISTENT, STANDARD SET OF MAPS DETAILING THE PIPELINE ROUTE IN ALASKA. EACH STATE AND FEDERAL AGENCY HAS DATA PERTINENT TO THEIR MISSION; HOWEVER, SHARING THAT DATA AND INCORPORATING IT INTO ONE AUTHORITATIVE BASEMAP IS INSTRUMENTAL TO EXPEDITE PERMITTING. BY THE END OF THE YEAR, WE’LL HAVE INTEGRATED INFORMATION ON A 20-MILE STRETCH OF THE ROUTE AT ATIGUN PASS.
OUR GOAL IS TO DEMONSTRATE THAT THE GIS PROTOTYPE IS AN AUTHORITATIVE, CONSISTENT, AND INTEGRATED SOURCE OF INFORMATION THAT SHOULD BE USED BY ALL PARTIES TO PERMIT, DESIGN, CONSTRUCT, OPERATE, AND MAINTAIN A GAS PIPELINE. CLICK
SLIDE 10 – IMPROVEMENT IN DATA QUALITY
EXISTING ELEVATION DATA FOR THE AREA IS COARSE. LIDAR DATA REVEALS THE TERRAIN IN FAR MORE DETAIL. OUR SYSTEM USES THE INCREDIBLY DETAILED LIDAR AS THE BASE MAP. CLICK
SLIDE 11 – SLOPE
HERE IS A DETAIL VIEW OF ATIGUN PASS. THE LIDAR DATA THAT WE COLLECTED THIS FALL HAS BEEN ANALYZED IN GIS TO SHOW SLOPE. SHOWN HERE IS SLOPE IN DEGREES, BLUE COLOR BEING FROM 0—7 DEGREE SLOPES; AND RED COLOR 7—90 DEGREE SLOPES. THE INTENSITY OF COLOR REFLECTS SLOPE STEEPNESS. ALSO SHOWN HERE ARE THE ORIGINAL NORTHWEST BOREHOLES. MORE THAN 1,000 BOREHOLES WERE DIGITIZED AS PART OF THIS PROTOTYPE PROJECT, WHICH IS ONLY 20 MILES LONG. CLICK
SLIDE 12 – WEB ACCESS TO DATA
THE WEB BROWSER APPLICATION WILL PROVIDE PUBLIC ACCESS TO THE GIS DATABASE. DATA CAN BE SELECTED TO BE DISPLAYED DEPENDING ON LEVELS OF CONFIDENTIALITY. IN THIS CASE WE ARE LOOKING AT THE OVERVIEW OF THE ATIGUN PASS PROTOTYPE AREA ON TOP OF THE REGIONAL ELEVATION BASE OVERLAID WITH SATELLITE IMAGERY. THE TABLE OF CONTENT FRAMES ON THE LEFT SHOW THE ATIGUN PASS PROTOTYPE LAYERS. THESE ARE BY DEFAULT TURNED OFF AT THE BEGINNING AND CAN BE TURNED ON ONE BY ONE. NOTE, THAT EACH LAYER WILL HAVE ITS OWN SECURITY/CONFIDENTIALITY LEVEL. IT IS OUR GOAL TO MAKE AS MUCH INFORMATION AVAILABLE TO THE PUBLIC AS POSSIBLE. CLICK
SLIDE 13 – INCORPORATING GEOTECHNICAL DATA
NORTHWEST BOREHOLE LOGS ARE GEOREFERANCED INTO THE GIS PROTOTYPE AND PROVIDE A STRATIFICATION OF SOIL TYPES AND PERMAFROST DATA. THERE ARE MORE THAN 10,000 BOREHOLES IN ALASKA ALONE BUT THE DATA HAS NEVER BEEN INTEGRATED.
WITH GIS, YOU CAN CLICK ON ANY POINT ALONG THAT STRETCH OF THE PIPELINE TO EXTRACT AND VIEW RELEVANT MAPPING AND REPORT DATA. THE POWER OF GIS IS PROVIDING A PLATFORM FOR SHOWING MANY TYPES OF INFORMATION. CLICK
SLIDE 14 – INTEGRATING DATA
IN THIS CASE WE ARE CLICKING ON A STREAM CROSSING POINT (IN GREEN SQUARES) TO PULL UP A PHOTO. WE THEN CAN CLICK ON A STREAM TO GET INFORMATION ABOUT THAT STREAM, ITS NAME AND ESSENTIAL FISH HABITAT. THE PIPELINE IS SHOWN IN RED, THE PROPOSED GASLINE MILEPOSTS IN YELLOW. CLICK
SLIDE 15 – KEY FINDINGS
TO SUMMARIZE, THE GIS PROTOTYPE WILL PROVIDE AN:
• AUTHORITATIVE BASEMAP, WHICH ALLOWS DATA TO BE INTEGRATED FOR MULTIPLE AGENCIES, THE PUBLIC AND STAKEHOLDERS;
• THE WEB INTERFACE PROVIDES TRANSPARENT ACCESS TO DATA AT DIFFERENT LEVELS; AND
• LIDAR COUPLED WITH GOOD IMAGERY PROVIDES A VALUE-ADDED DATABASE.
LET ME TOUCH BRIEFLY ON SOME MORE OF THE TECHNICAL CHALLENGES THE PIPELINE PROJECT FACES. CLICK
SLIDE 16 - TECHNICAL ISSUES
MUCH OF THE LAND ALONG THE PIPELINE ROUTE IN ALASKA CONTAINS PERMAFROST. PERMAFROST IS DEFINED AS GROUND THAT DOES NOT THAW FOR TWO OR MORE YEARS AND CAN REACH THICKNESS OF MORE THAN 1,000 FEET. PERMAFROST EXTENDS THROUGH AS MUCH AS 50 PERCENT OF CANADA AND 80 PERCENT OF ALASKA (CLARK, 1988). IT IS CONTINUOUS IN THE NORTH, DISCONTINUOUS IN THE MID-SECTIONS AND LEADS TO AREAS NEAR THE 60TH PARALLEL THAT ARE SUBJECTED TO ONLY SEASONAL FREEZING. BUT EVEN THAT FREEZING AND THAWING CAN CAUSE THE LAND TO SHIFT DRAMATICALLY PLACING MAJOR STRESS ON A BURIED, CHILLED PIPELINE.
PERMAFROST TRENDS MUST BE INCORPORATED INTO THE DESIGN BY PROJECT ENGINEERS FOR THIS 30-PLUS-YEAR PIPELINE. THE UNIVERSITY OF ALASKA, STATE OF ALASKA DEPARTMENT OF GEOLOGICAL AND GEOPHYSICAL SURVEYS, AND U.S. GEOLOGICAL SURVEY HAVE BEEN WORKING TOGETHER TO MAP AND UNDERSTAND THE CHANGE THAT IS OCCURRING. CLICK
SLIDES 17 – 47 – PERMAFROST MAP
ON THE SCREEN IS A MODEL THAT DEMONSTRATES THE RANGE OF PERMAFROST IN ALASKA FROM 1950 TO TODAY AND HOW IT IS FORECAST TO SHIFT BY 2100. THE AREAS IN RED ARE PERMAFROST FREE AND AS YOU LOOK FURTHER NORTH THE COLORS SHIFT TO LIGHT BLUE AND DARK BLUE AREAS – THE DARKER THE BLUE, THE COLDER THE GROUND TEMPERATURE. WATCH CLOSELY WHAT IS FORECAST TO HAPPEN – THE TREND IS STARTTLING! CLICK
(PAUSE WHILE SLIDE SHOW RUNS SLIDES 17-47)
CLICK
SLIDE 48 - ARCTIC CONSTRUCTION AND ENGINEERING
FROST HEAVE AND BUCKLING OF PIPELINES ARE KNOWN MAJOR CAUSES OF NATURAL GAS PIPELINE FAILURES IN THE ARCTIC.
THE GEOLOGIC INSTABILITY OF ROUTES THROUGH PERMAFROST PUT CHALLENGING DEMANDS ON THOSE WHO DESIGN AND CONSTRUCT PIPELINES IN COLD REGIONS.
ARCTIC CONSTRUCTION AND ENGINEERING IS ANOTHER SIGNIFICANT CHALLENGE. CONSTRUCTION IN ALASKA WILL TAKE PLACE PRIMARILY IN WINTER SEASONS, WHERE TEMPERATURES CAN REACH 60 BELOW ZERO. LACK OF SUN AND THE DARKNESS INCREASE THE POTENTIAL FOR ACCIDENTS, UNSAFE CONDITIONS, AND WORKER FATIGUE. MACHINERY TENDS TO NOT FUNCTION IN THE SAME CAPACITY IN EXTREME WIND AND COLD.
THIS WILL BE THE LARGEST HIGH-PRESSURE GAS PIPELINE EVER BUILT IN THE ARCTIC. PHMSA AND THE CANADIAN NATIONAL ENERGY BOARD WILL HARMONIZE REQUIREMENTS ON BOTH SIDES OF THE BORDER TO WITHSTAND THE EXTREME ARCTIC CONDITIONS. THEY HAVE ALREADY BEGUN THIS WORK. CLICK
SLIDE 49 – SEISMIC ACTIVITY ROAD DAMAGE
ON AVERAGE, ALASKA RECORDS 50 TO 100 EARTHQUAKES PER DAY, ONE MAGNITUDE-7 EVENT EVERY YEAR AND A MAGNITUDE-8 OR LARGER EVENT EVERY 13 YEARS. AS A RESULT OF ITS SEISMICITY, REGIONS OF ALASKA DO IN FACT POSE SIGNIFICANT CHALLENGES TO THE CONSTRUCTION OF A NATURAL GAS PIPELINE. MOST ALASKANS FELT THE DENALI FAULT LINE MAGNITUDE-7.9 EARTHQUAKE THAT OCCURRED ON NOVEMBER 3, 2002. THAT FAULT SLIPPED APPROXIMATELY 18 FEET LATERALLY AND MORE THAN 3 FEET VERTICALLY BENEATH THE TRANS ALASKA PIPELINE SYSTEM. NOT ONE DROP OF OIL SPILLED FROM THE PIPELINE. WHY? CLICK
SLIDE 50 – SEISMIC ACTIVITY FAULT MAPS
BECAUSE THE SEISMIC ACTIVITY IN SOUTH CENTRAL ALASKA WAS UNDERSTOOD BY THE ENGINEERS AND GEOLOGISTS WHO PLAYED A ROLE IN THE DESIGN, PLACEMENT, AND LOCATION OF TRANS ALASKA PIPELINE SYSTEM SOME THIRTY YEARS EARLIER.
INNOVATIVE GEOLOGICAL AND GEOPHYSICAL ENGINEERING WILL BE NEEDED WHERE THE GAS PIPELINE CROSSES ACTIVE FAULTS TO DESIGN A PIPELINE THAT WILL BE “FAIL SAFE.” FOR EXAMPLE, WHERE THE GAS LINE FOLLOWS THE ALASKA HIGHWAY FROM DELTA JUNCTION INTO CANADA IT WILL CROSS SOME NORTHEAST-TRENDING FAULTS. THIS PART OF THE PIPELINE ROUTE WAS CONSIDERED TO BE A REGION OF LOW SEISMIC ACTIVITY. BUT THE LATEST WORK BY THE STATE OF ALASKA DEPARTMENT OF GEOLOGICAL AND GEOPHYSICAL SURVEYS INDICATES SUBSTANTIAL RECENT ACTIVITY IN THE REGION. NEW DESIGN STANDARDS WILL BE REQUIRED IN THIS AREA. CLICK
SLIDE 51 – RIGHTS OF WAY
IN ALASKA, THIS PIPELINE WILL TRAVERSE 750 MILES ALONG FEDERAL, STATE, PRIVATE AND NATIVE ALLOTMENT LANDS, REQUIRING RIGHTS-OF-WAY FOR THE ENTIRE ROUTE.
ON THE CANADIAN SIDE, THE ROUTE IS NEARLY 1,000 MILES LONG. BOTH COMPANIES ARE PROGRESSING THEIR CANADIAN PERMIT PROCESSING. CLICK
SLIDE 52 - ECONOMIC ISSUES
THERE ARE FIVE MAJOR ECONOMIC ISSUES FOR THIS PROJECT.
 FIRST, FINANCING FOR THE LARGEST AND MOST INNOVATIVE NATURAL GAS TRANSPORTATION SYSTEM EVER CONSTRUCTED. THE PRIVATE SECTOR WILL FINANCE THIS PROJECT. CONGRESS ALSO AUTHORIZED A LOAN GUARANTEE OF UP TO 18 BILLION DOLLARS IN 2004 DOLLARS THAT WILL BE ADJUSTED FOR INFLATION. IN ADDITION CONGRESS IS NOW CONSIDERING INCREASING IT TO $30 BILLION.
 SECOND, THE GROWING SECTOR OF UNCONVENTIONAL NATURAL GAS – NAMELY SHALE – WHICH BRINGS NEW VARIBLES INTO THE EQUATION;
• THIRD, IT IS IMPERATIVE TO HAVE THE NECESSARY INFRASTRUCTURE IN PLACE TO STAGE ALL THE MANPOWER AND MATERIALS FOR CONSTRUCTION. IN BOTH THE U.S. AND CANADA, THE COMPANIES ARE TALKING TO THE APPROPRIATE ENTITIES ABOUT WHAT NEW BRIDGES, HIGHWAYS, AIRPORTS, MATERIAL SITES AND MAINTENANCE CAMPS WILL BE NEEDED TO SUPPORT TENS OF THOUSANDS OF WORKERS, THE HEAVY EQUIPMENT AND THE 2.5 MILLION TONS OF STEEL TO CONSTRUCT THE PIPELINE. THE COMPANIES WILL BE RESPONSIBLE FOR THESE INFRASTRUCTURE NEEDS.
 FOURTH, THE PROJECT CALLS FOR MASSIVE AMOUNTS OF STEEL. IN ANGPA, CONGRESS EXPRESSED THE PREFERENCE THAT SUCH STEEL SHOULD COME FROM NORTH AMERICA. NORTH AMERICAN STEEL PRODUCERS AND PLANTS WILL NEED TO BE PREPARED TO DELIVER 2.5 MILLION TONS OF HIGH STRENGTH STEEL FOR THE ENTIRE PROJECT. CLICK
SLIDE 53 – WORK FORCE
THE LAST ECONOMIC ISSUE IS FINDING, TRAINING AND RETAINING THE LABOR POOL NEEDED ON BOTH SIDES OF THE BORDER. LABOR FOR CONSTRUCTION OF THE TRANS-ALASKA PIPELINE SYSTEM PEAKED AT 28,000. CLICK
SLIDE 54 - JOBS
THIS GAS PIPELINE WILL REQUIRE TENS OF THOUSANDS OF SKILLED WORKERS AT THE PEAK AS WELL. A HUGE SKILLED LABOR FORCE MUST BE TRAINED, BE READY TO BE HIRED, AND THEN RETAINED THROUGHOUT THE PRECONSTRUCTION AND CONSTRUCTION. CANADA’S LABOR CHALLENGES WILL COMPLEMENT OURS.
IT IS A FULLY ENGAGED PROCESS WITH MANY COMPONENTS. CLICK
SLIDE 55 – OUR PARTNERSHIP WITH CANADA
LET ME TAKE A MINUTE TO BRIEF YOU ON MY WORK WITH OUR CANADIAN PARTNERS. IT’S IN OUR BEST INTEREST TO ENSURE THE PROCESS MOVES AS EXPEDITIOUSLY AS POSSIBLE ON THEIR SIDE OF THE BORDER.
AT THIS POINT, EVERYONE IS ENGAGED. MINISTER JIM PRENTICE – WHO HAS THE ALASKA PIPELINE FILES ON HIS DESK – NATURAL RESOURCES MINISTER LISA RAITT, DEPUTY NATURAL RESOURCES MINISTER CASSIE DOYLE, THE NATIONAL ENERGY BOARD, THE NORTHERN PIPELINE OFFICE, THE MPMO, THE ENVIRONMENTAL ASSESSMENT AGENCY, PROVINCIAL PREMIERS, THE FEDERAL SENATE, THE PETROCHEMICAL INDUSTRY, ORGANIZED LABOR, FIRST NATIONS, ET AL ARE ENGAGED AND ENTHUSIASTIC ABOUT THE ECONOMIC BENEFITS THAT THE PIPELINE WILL BRING TO CANADA.
WE’VE INVITED CANADIANS TO BE A PART OF THE TECHNICAL REVIEW TEAM – THEY HAVE EXPERTS AND EXPERIENCE THAT ARE OF CRITICAL IMPORTANCE TO THE U.S. PERMITTING AGENCIES.
ALL THOSE CANADIAN OFFICIALS I MENTIONED HAVE SHAKEN MY HAND AND PLEDGED TO MEET THE U.S. SCHEDULE SO THAT THE CANADIAN LICENSES ARE IN PLACE WHEN FERC ISSUES THE U.S. LICENSES.
CANADA DOESN’T HAVE A POSITION LIKE MINE, BUT MINISTERS PRENTICE AND RAITT HAVE BEEFED UP THE MPMO TO BE THE PROJECT MANAGER FOR DENALI AND REPOPULATED THE NORTHERN PIPELINE AGENCY TO OVERSEE THE ALASKA PIPELINE PROJECT.
SLIDE 56 – STATE OF ALASKA
I WOULD BE REMISS IF I DIDN’T MENTON THE OFC WORK WITH THE STATE OF ALASKA. THE OFC AND STATE OF ALASKA ATTORNEYS ARE WORKING ON A DRAFT SURVEILLANCE AND MONITORING AGREEMENT, WHICH IS REQUIRED BY OUR STATUTE. WHEN FINALIZED, THE MOU WILL LAYOUT THE PROCESS IN DETAIL FOR WORKING TOGETHER FROM THE PERMITTING PHASE OF THE PROJECT THROUGH CONSTRUCTION.
THIS PROJECT, AS I SAID AT THE BEGINNING OF MY PRESENTATION, IS CRITICAL TO NORTH AMERICAN ENERGY SECURITY. THERE IS AN ABUNDANCE OF NATURAL GAS ON ALASKA’S NORTH SLOPE; THERE IS NATIONAL SUPPORT FOR THE PIPELINE PROJECT INCLUDING AN ENDORSEMENT FROM THE NATIONAL AFL-CIO BECAUSE OF THE TENS OF THOUSANDS OF GOOD PAYING, GREEN JOBS IT WILL CREATE. THERE’S SUPPORT FROM CONGRESS AND THE WHITE HOUSE AS WELL.
FIRST GAS IS PLANNED FOR 2018, FOLLOWING FERC LICENSING IN 2014. THAT MAY SEEM LIKE A LONG TIME, BUT 2014 FINANCING AND SANCTIONING IS RIGHT AROUND THE CORNER. CLICK
SLIDE 57 – OFC CONTACT INFO SLIDE
IT’S BEEN AN HONOR TO STAND UP THE OFC AND DEVOTE EVERY DAY TO THE COMMERCIALIZATION OF ALASKA’S NORTH SLOPE GAS. THANK YOU FOR THIS TIME TO UPDATE YOU. IT HAS BEEN A TRUE PLEASURE WORKING WITH YOU AND SERVING ON THIS ADVISORY COMMITTEE.

Attachments: 

The Alaska Natural Gas Project: What The Future Holds

Document Type: 
Speech
Release Date: 
09/10/2009

THE ALASKA NATURAL GAS PROJECT:
WHAT THE FUTURE HOLDS

Presented Sept. 10, 2009
To the Rocky Mountain Mineral Law Conference
Energy Development: Access, Siting,
Permitting and Delivery on Public Lands
Denver, CO

by Drue Pearce
Federal Coordinator
Office of the Federal Coordinator
Alaska Natural Gas Transportation Projects

SLIDE 1: COVER PAGE
Thank you for the kind introduction and for the invitation to be here with you in Denver. I’ll begin this afternoon by telling you that this natural gas pipeline being planned for construction from Alaska through Western Canada to the US Midwest is a complex undertaking encompassing every aspect of my organization’s mission and multiple federal, state and private sector stakeholders.
From the federal perspective, and as an Alaskan, I always chuckle at the characterization that Alaska doesn’t want to have much to do with anyone or anything “outside” the state. Some would have you believe that Alaska is a resource-rich developing country – which is true – with weak institutions, woeful oversight – not true – and a bad habit of referring to every other place on earth with a single word: “Outside.”
OK, so in fact, Alaskans do use that term but I can assure you that with regard to this project Alaska is all about going ‘outside’ its borders to get it done. Through the Office of the Federal Coordinator, Alaska is involved with more than 20 federal agencies, with the Canadians, and many other stakeholders. CLICK

SLIDE 2: GAS PIPELINE ROUTE
So, I’m happy to report to you that we are moving forward. In recent months there has been much progress and even I would say a game changing partnership when ExxonMobil joined the TransCanada Alaska team. CLICK

SLIDE 3: FEDERAL FAMILY IN ALASKA
I was in Alaska last month with eight administration and federal agency officials who are part of the federal family of those 20 plus agencies – all of which have an important role in bringing this project online. Although we had only 8 with us, it was the first time most of them had seen the scope of what it will take to bring arctic gas to North American markets. They gained an important sense of geography and the complexity of the pipeline project as well as its potential importance to U.S. energy security, the domestic economy and the environment. CLICK
SLIDE 4: FEDERAL FAMILY IN ALASKA
We had a very successful outcome in getting them in country, giving them the best briefings by knowledgeable experts and establishing important relationships for the future.
We discussed the challenges and opportunities associated with the natural gas pipeline, and fresh from that trip, I want to review with you where we are today. CLICK

SLIDE 5: U.S. CAPITOL
First of all, in the coming months as the Congress debates climate change, energy security and the need for sources of clean energy, Americans will begin to hear more about the fact that Alaska holds one of the largest known reserves of natural gas in the North America. CLICK

SLIDE 6: MAP OF PIPELINE ROUTES
The 35 trillion cubic feet of proven natural gas reserves will make a significant long-term contribution to the United States’ energy security, and getting a natural gas pipeline built is a priority of the Obama Administration. CLICK

SLIDE 7: JOBS AND OIL FIELD WORKERS
But the pipeline means more than just providing clean energy. It is at least a $26 billion dollar, privately funded stimulus plan. And if we want to generate long-term economic growth, we need the type of private sector created jobs that this project will create. Over the lifecycle of the project, it will provide tens of thousands of jobs to American workers – not just in building the pipeline but indirectly to places like the steel mills where the rolls of steel will be created and in the transportation, security, food and even the banking industries, all of which will be critical in supporting this project. CLICK

SLIDE 8: INTERACTING WITH CANADA
The project also creates a new means to interact with our Canadian neighbors and all stakeholders. And it will help give America the energy security that it needs to help wean the United States off overseas dependence. CLICK

SLIDE 9: TAPS PIPELINE
Today there is a renewed national interest in the Alaska gas pipeline. When the Trans Alaska Pipeline System was being constructed, plans were initiated to build a large diameter pipeline to deliver natural gas to the lower 48. CLICK

SLIDE 10: PRESIDENT JIMMY CARTER
Congress enacted the Alaska Natural Gas Transportation Act and President Carter designated the route, design and project sponsors a transportation system. CLICK

 

SLIDE 11: ANGTA MAP
The ANGTA designated right of way for the natural gas pipeline would have run from Prudhoe Bay to Delta Junction then east into Canada, across the Yukon Territory and finally south to the lower 48 states. In the 1980’s a portion of the pipeline was built from Alberta Canada south to San Francisco, California and Chicago, Illinois. In effect, we are now working to complete the Northern part of the route.
There have been multiple proposals to produce North Slope gas and move it south since the late 1970’s. The current began with Congress passing the Alaska Natural Gas Pipeline Act, known as ANGPA in 2004. That statute created the Office of the Federal Coordinator for Alaska Natural Gas Transportation Projects, and I was sworn in as the Federal Coordinator in 2006. CLICK

SLIDE 12: AGIA LEGISLATION
In 2007 and 2008, the State of Alaska moved forward with the Alaska Gasline Inducement Act (AGIA), creating a $500 million financial partnership with TransCanada Alaska. It is important to note that the AGIA license does not grant an exclusive right to land use and right-of-way permits.
As I mentioned a bit earlier, TransCanada Alaska recently announced a partnership with ExxonMobil and has entered the FERC Pre-file Process. CLICK

SLIDE 13: DENALI LOGO
Last year, Denali, a joint venture of ConocoPhillips and BP, developed a competing project outside of AGIA and was granted the right to proceed in the Pre-File Process with the U.S. Federal Energy Regulatory Commission, FERC. Both proposals follow the same route as contemplated by President Carter in 1977. CLICK

SLIDE 14: OFC LOGO
For those of you who are unfamiliar with our role in the process, let me step back and give you a very brief overview. CLICK

SLIDE 15: OFC DESCRIPTION
The Office of Federal Coordinator for Alaska Natural Gas Transportation Projects (OFC) has a congressional mandate to expedite the federal pipeline’s permitting, construction and operation.
More than 20 federal agencies will participate in the planning and approval process for this pipeline project, and it will be our job to identify and develop strategies to overcome potential regulatory bottlenecks and otherwise expedite regulatory approvals.
Federal law prohibits federal agencies from including any term or condition that the Federal Coordinator determines would prevent or impair in any significant respect the expeditious construction and operation, or expansion, of the Alaska gas pipeline project.
The law gives my office the responsibility for developing a Surveillance and Monitoring Agreement with the State of Alaska. We are currently working on an Agreement that will layout the process for working together from the permitting phase of the project through construction.
Lastly, my staff and I meet regularly with Canadian officials working on this project to identity and resolve any cross-border issues as early as possible. We also are in close contact with the Governor and State of Alaska officials. And, we work hard on being transparent through all of our communications efforts. We want you to know what we know, and we’re committed to providing all stakeholder groups and the public with the most comprehensive and accurate project information possible. CLICK

SLIDE 16: CHALLENGES
So, other than trying to manage some 20 plus federal agencies, work with the State of Alaska and the government of Canada, along with keeping the interests of the indigenous people at the forefront of our consideration, what are the major challenges?
I love a good challenge, and we have identified a couple of categories that definitely fit the description.
The most straightforward but hardly simplest of the issues are the technical ones. They are solvable but will require collaboration between hydrologists, biologists, archaeologists, geologists, metallurgists, ecologists, climatologists, seismologists and engineers of all classes to name a few.
There are also economic issues: A few minutes ago, I mentioned the jobs that will be created in the steel industry. That’s because the project will utilize approximately 2.5 million tons of steel and a 2004 estimate had the project creating 54 million hours of work. At the same time the cost of the project will need to be financeable by the middle of the next decade and the tariffs have to be low enough to attract customers. CLICK

SLIDE 17: Technical Issues
Let’s start with the technical challenges: CLICK

SLIDE 18: Permafrost Construction
Much of the land along the pipeline route in Alaska contains permafrost. Permafrost is defined as ground that does not thaw for two or more years and can reach thickness of more than 1,000 feet. Permafrost extends through as much as 50 percent of Canada and 80 percent of Alaska (Clark, 1988). It is continuous in the North, discontinuous in the mid-sections and leads to areas near the 60th parallel that are subjected to only seasonal freezing. But even that freezing and thawing can cause the land to shift dramatically placing major stress on a buried, chilled pipeline. CLICK

SLIDE 19 TO 34: Permafrost Map Slide Show
Permafrost trends must be incorporated into the design by project engineers for this 30-plus-year pipeline. The University of Alaska, State of Alaska Department of Geological and Geophysical Surveys, and U.S. Geological Survey have been working together to map and understand the change that is occurring. On the screen is a model that demonstrates the range of permafrost in Alaska from 1950 to today and how it is forecast to shift by 2100. The areas in red are permafrost free and as you look further north the colors shift to light blue and dark blue areas – the darker the blue, the colder the ground temperature. Watch what is forecast to happen. CLICK
(PAUSE while slide show runs)

SLIDES 35 TO 45: Permafrost Map Slide Show One More Time – 2000-2050
I am going to play the map one more time showing you the map from 2000 to 2050. This time, we look at the forecast change every 5 years. CLICK
(PAUSE while slide show runs)
CLICK

SLIDE 46: ARCTIC CONSTRUCTION AND ENGINEERING
Frost heave and buckling of pipelines are known major causes of natural gas pipeline failures in the Arctic.
The geologic instability of routes through permafrost put challenging demands on those who design and construct pipelines in cold regions. CLICK

SLIDE 47: BURIED PIPE
Arctic construction and engineering is another significant challenge. Construction in Alaska will take place primarily in winter seasons, where temperatures can reach 60 below zero. Lack of sun and the darkness increase the potential for accidents, unsafe conditions, and worker fatigue. Machinery tends to not function in the same capacity in extreme wind and cold. People are working in the Arctic every day, so these are very manageable issues.
This will be the largest high-pressure gas pipeline ever built in the Arctic. The U.S. Pipeline and Hazardous Materials Safety Administration and the Canadian National Energy Board will harmonize requirements on both sides of the border to withstand the extreme Arctic conditions. They have already begun this work. CLICK

SLIDE 48: SEISMIC
On average, Alaska records 50 to 100 earthquakes per day; one magnitude-7 event every year; and a magnitude-8 or larger event every 13 years. As a result of its seismicity, regions of Alaska do in fact pose significant challenges to the construction of a natural gas pipeline. Most Alaskans felt the Denali Fault Line magnitude-7.9 earthquake that occurred on November 3, 2002. That fault slipped approximately 18 feet laterally and more than 3 feet vertically beneath the Trans Alaska Pipeline System. Not one drop of oil spilled from the pipeline. Why? Because the seismic activity in south central Alaska was understood by the engineers and geologists who played a role in the design, placement, and location of Trans Alaska Pipeline System line some thirty years earlier. CLICK

SLIDE 49: DELTA JUNCTION
Innovative geological and geophysical engineering will be needed where the gas pipeline crosses active faults to design a pipeline that will be “fail safe.” For example, where the gas line follows the Alaska Highway from Delta Junction into Canada it will cross some northeast-trending faults. This part of the pipeline route was considered to be a region of low seismic activity. But the latest work by the State of Alaska Department of Geological and Geophysical Surveys indicates substantial recent activity in the region. New design standards will be required in this area. CLICK

SLIDE 50: CONGRESSIONAL ACTION
As Congress debates climate change and energy policy in this legislative session, I continue to remind lawmakers about the benefits of this project vis-a-vis their desire to see a climate change bill passed this session.
Natural gas can serve as an efficient and cost effective bridge fuel as the nation moves toward establishing new sources of energy – wind, solar and geothermal to name a few -- and natural gas can deliver immediate reductions in greenhouse gases. CLICK

SLIDE 51: ARCTIC WARMING
Congressional action aside, it is very important that policy makers understand permafrost changes and other effects climate change may have on the pipeline after its construction. In October 2008, Canada and the U.S. held the first Northern Oil and Gas Research Forum. The forum provided an opportunity for the two countries to bring together scientists, resource managers and industry to discuss what research is being conducted and to identify gaps. While not limited to climate change, the goal of the forum was to initiate a cooperative effort in which the research that is being done is the research that policy makers need to make the decisions of the day. CLICK

SLIDE 52: RIGHT-OF-WAY
One such decision they need to make that will be of particular interest to you pertains to the pipeline rights-of-way.
In Alaska, this pipeline will traverse 750 miles along federal, state, private and Native allotment lands.
On the Canadian side, the route is nearly 1,000 miles long. TransCanada, through its Canadian subsidiary Foothills Pipeline Company, claims that it already has most of the access rights and certificates that it needs to build the pipeline in Canada by virtue of its approvals under the 1978 Northern Pipeline Act.
The other applicant, Denali, also plans to apply for a right-of-way along the Alaska Highway corridor through Canada.
Canada’s Major Projects Management Office will oversee Denali’s application process. CLICK

SLIDE 53: ECONOMIC CHALLENGES
With all of the invigorating challenges presented by the technical and legal issues, I’d like to turn my comments to the economic issues, which are equally as grand. Depending on how you look at it, there are five major economic challenges or benefits for this project. CLICK


SLIDE 54: ECONOMIC CHALLENGES
First, this is a $26 billion dollar enterprise, according to the latest estimate. Who will finance the largest and most innovative natural gas transportation system ever constructed? The private sector will finance this project. It is true that Congress also authorized a loan guarantee of up to 18 billion dollars in 2004 dollars that will be adjusted for inflation and is considering increasing it to $30 billion. The loan guarantee is likely to be an essential piece of the financial puzzle; however the private sector will take on the responsibility for financing the projects debt.
Second, in order to construct a pipeline, it is imperative to have the necessary infrastructure in place to stage all the manpower and materials for construction.
In both the U.S. and Canada, the companies are talking to the appropriate entities about what new bridges, highways, airports, material sites and maintenance camps will be needed to support tens of thousands of workers, the heavy equipment and the 2.5 million tons of steel to construct the pipeline. The companies will be responsible for these infrastructure needs.
It will take 4-6 years to complete the major infrastructure projects. They must be done before pipeline construction can begin. Every day, week, month, year that we wait to build the infrastructure adds major costs to the project. CLICK

SLIDE 55: STEEL NEEDS
Third, the project calls for all that steel. In ANGPA, Congress expressed the preference that such steel should come from North America. North American steel producers and plants need to be prepared to deliver 2.5 million tons of high strength steel pipe in the next decade. CLICK

SLIDE 56: QUALIFIED LABOR
The fourth economic challenge is finding, training and retaining the labor pool needed on both sides of the border. Labor for Trans Alaska Pipeline System peaked during construction at 28,000 workers ranging from welders to truck drivers to cooks.
This pipeline will require tens of thousands of skilled workers at the peak. A huge skilled labor force must be trained, be ready to be hired, and then retained throughout the preconstruction and construction.
The U.S. Dept. of Labor gave to the State of Alaska a grant it is using to conduct a study as well as to begin finding and training that labor pool. CLICK

SLIDE 57: PIPELINE APPLICANTS
Finally, I want to note that Denali and TransCanada Alaska are engaged in the regulatory process for the gas line construction. Both interests are following the same highway corridor, but they have a different means to getting the project done. Both are earnest in their desire to be the company that builds the pipeline.
Of course Trans Canada holds the state of Alaska’s license and, as I mentioned, three months ago, TransCanada Alaska announced ExxonMobil as its new partner. Both Denali and TransCanada Alaska have been in the field for the past two seasons conducting environmental and other studies, and both are moving toward “open season” next year wherein North Slope producers will have an opportunity to commit natural gas to the pipeline for transport to lower 48 markets.
It is a fully engaged process with many components, and I am sure you would agree that expediting this confluence of interests and the permitting and technical issues may seem daunting. CLICK

SLIDE 58: WINSTON CHURCHILL
But when the process seems slow, I’m reminded of Winston Churchill who advised to never, never, never give up.
You might know that it was Churchill who, as a member of the War Council of Great Britain, acquired a majority interest in the Anglo-Persian Oil Company in 1914, bringing the company under British government control to secure its access to Persian oil. That company later became British Petroleum.
When I look at the complexity of this project and all of the competing and complementary interests, I’m reminded of Churchill’s foresight in bringing energy security to Great Britain and of his words, which I leave you with today… CLICK

SLIDE 59: CHURCHILL SAID
He said: “Success is not final, failure is not fatal; it is the courage to continue that counts.”
As President Obama works toward presenting Congress with a national energy plan that includes an emphasis on clean natural gas and renewable energy sources, this project makes economic sense, and we need the courage to complete this project and bring arctic natural gas to North American markets within the next 10 years.
Our nation will benefit plenty if we do. CLICK

SLIDE 60: OFC CONTACT INFO
Thank you and I look forward to taking your questions.
 

Attachments: 

Update on Federal Activities Toward Coordinating The Alaska Natural Gas Pipeline

Document Type: 
Speech
Release Date: 
11/19/2009

UPDATE ON FEDERAL ACTIVITIES TOWARD COORDINATING THE
ALASKA NATURAL GAS PIPELINE

Presented Nov. 19, 2009
To the Resource Development Council’s Annual Meeting
Anchorage, Alaska

by Drue Pearce
Federal Coordinator,
Alaska Natural Gas Transportation Projects
Washington, DC


IT’S ALWAYS GREAT TO BE HOME. TODAY IS ESPECIALLY POIGNANT AS IT IS LIKELY MY FINAL APPEARANCE BEFORE THE RDC IN MY ROLE AS YOUR FEDERAL COORDINATOR.
I WANT TO THANK YOU, JASON, CARL AND MEMBERS FOR ALL YOU DO FOR ALASKA.
AS YOU KNOW, AT THE REQUEST OF THE PRESIDENT, I TENDERED MY RESIGNATION AND JANUARY 3RD WILL BE MY FINAL DAY AS YOUR FEDERAL COORDINATOR. I WANT TO TAKE THIS OPPORTUNITY TO TELL YOU AND ALL ALASKANS THAT IT’S BEEN AN EXCEPTIONAL HONOR TO BE THE FIRST FEDERAL COORDINATOR. MY MISSION ALL DAY, EVERY DAY, HAS BEEN TO EXPEDITE THE MOST IMPORTANT ENERGY DEVELOPMENT PROJECT IN NORTH AMERICA.
THE COMMERCIALIZATION OF NORTH SLOPE GAS PROJECT IS CRITICAL NOT JUST TO ALASKA BUT TO THE NATION, AND AS THE OFC MISSION STATEMENT SAYS IT IS OUR JOB TO: “Advance our Nation’s energy and economic security by expediting the delivery of clean, natural gas from the North Slope of Alaska to North American markets.
I AM VERY PROUD OF WHAT I’VE ACCOMPLISHED OVER THE PAST THREE YEARS. I’VE STOOD UP A NEW INDEPENDENT FEDERAL AGENCY WITH A SECURE BUDGET, A GREAT STAFF, AN UNQUALIFIED ANNUAL AUDIT -- FOR ALL YOU CPA’S IN THE ROOM, YOU KNOW WHAT AN ACCOMPLISHMENT THAT IS -- AND A SOLID STRATEGIC PLAN. I AM EVEN MORE PROUD OF WHAT MY STAFF AND I HAVE DONE AS A TEAM TO PREPARE THE FEDERAL GOVERNMENT TO EXPEDITE THE PROJECT.
I REGRET HAVING TO LEAVE BEFORE THE JOB IS DONE. SO THIS MORNING, PLEASE ALLOW ME TO GIVE YOU MY VERSION OF THE “STATE-OF-THE-STATE” SPEECH – A STATE OF THE AGENCY SPEECH.
CONGRESS AND A SUCCESSION OF PRESIDENTS RECOGNIZED A VERY DISTINCT NEED FOR AN OFFICE TO COORDINATE THE FEDERAL PROCESS OF LICENSING, PERMITTING AND OVERSIGHT OF DESIGN AND CONSTRUCTION OF THE GAS PIPELINE PROJECT. AT PRESIDENT JIMMY CARTER’S DIRECTION, THE OFFICE OF THE FEDERAL INSPECTOR PRESIDED OVER THE PRE-BUILD IN THE 80’S AND 90’S.
AFTER A NUMBER OF DRAFT ITERATIONS, THE OFC WAS CREATED IN 2004. IT TOOK 26 MONTHS TO GET FROM PASSAGE OF THE LEGISLATION TO MY SWEARING IN. I LIKE TO DESCRIBE THE OFFICE AS BEING TASKED WITH DOING THE JOB THAT COMBINES THE TALENTS OF TRAFFIC COP, DIPLOMAT, PSYCHIC, OMBUDSMAN, ANALIST AND ENGINEER.
IT HAS BEEN 36 MONTHS SINCE I WAS SWORN IN. WHEN I STARTED, IT WAS JUST ME WITH NO OFFICE OR BUDGET OR STAFF. I’VE PUT TOGETHER A TALENTED AND DEDICATED GROUP OF 10 PEOPLE WHO WORK BOTH HERE IN ALASKA AND IN WASHINGTON, DC ON YOUR BEHALF. THEY ARE EXTREMELY TALENTED, FULLY ENGAGED AND DEDICATED TO A SINGLE MISSION…. TO COORDINATE AND EXPEDITE THE WORK OF 24 PLUS FEDERAL AGENCIES WITH ROLES IN THE PERMITTING, LICENSING, CERTIFICATING THE PIPELINE.
ALL THE WHILE WE COORDINATED WITH THE CANADIAN GOVERNMENT, THE STATE OF ALASKA AND ALL STAKEHOLDERS… FROM TRIBES TO THE ENVIRONMENTAL COMMUNITY.
AND SO I’D BE REMISS IF I DIDN’T APPLAUD THE STAFF I LEAVE BEHIND. THEY ARE EXCEPTIONAL.
CONGRESS HAS AUTHORIZED A $9.6 MILLION BUDGET TO ACCOMPLISH OUR LAUNDRY LIST OF TASKS. I HAVE TIME TODAY TO TOUCH ON ONLY A FEW OF OUR MAJOR EFFORTS:
• WHAT’S GOING ON AT THE FEDERAL U.S. LEVEL AS WE PREPARE FOR THE OPEN SEASONS AND COMPLETE APPLICATIONS FROM TRANSCANADA/EXXON MOBIL AND DENALI;
• HOW MY OFFICE COLLABORATES WITH CANADA’S REGULATORY AGENCIES AND ORGANIZATIONS TO EXPEDITE THE PROCESS; AND,
• OUR WORK WITH THE STATE OF ALASKA TO MOVE THIS PROJECT ALONG.
WE COMPLETED A GAP ANALYSIS THAT IDENTIFIES GAPS – OVERLAPS THAT COULD JEOPARDIZE THE EFFORT TO EXPEDITE CONSTRUCTION.
AS YOU KNOW, DENALI AND TRANSCANADA / EXXON MOBIL HAVE ENTERED FERC’S PRE-FILING PROCESS. BOTH ARE WORKING ON THEIR OPEN SEASONS WITH TRANSCANADA SLATED TO GO FIRST AND CONCLUDE IN THE SUMMER OF 2010. DENALI ANTICIPATES CONDUCTING ITS OPEN SEASON IN THE LATTER PART OF NEXT NEAR.
WE HAVE WRITTEN AN IMPLEMENTATION PLAN FOR EACH APPLICANT TO DEVELOP AN AGREED UPON ROADMAP FOR EACH TO FOLLOW AS THEY PROGRESS TO FILING THEIR FERC APPLICATIONS. THESE PLANS ALLOW FOR EARLY COORDINATION … EARLY COORDINATION MEANS WE HAVE ADOPTED A PROJECT MANAGEMENT APPROACH BASED ON A COMMON UNDERSTANDING AND COMMITMENT TO THE PERMITTING PROCESS. THE IMPLEMENTATION PLANS ALSO ALLOW THE OFC TO MAKE SURE THAT ALL FEDERAL AGENCIES FULLY COMPLY WITH THE FEDERAL LAWS THAT GOVERN THIS UNIQUE PROJECT.
WE ALSO ARE COMPLETING A PERMITTING MATRIX – AN OVERALL PICTURE OF THE PERMITTING PROCESS – FOR EACH APPLICANT SO THAT ALL AGENCIES, BOTH COMPANIES, AND THE PUBLIC HAVE AN ORGANIZED AND AGREED UPON FRAMEWORK TO USE AS THEY PREPARE, REVIEW AND ISSUE PERMITS, LICENSES AND CERTIFICATIONS.
THE FERC’S SCHEDULE TO COMPLETE THE ENVIRONMENTAL IMPACT STATEMENT IS MORE THAN AMBITIOUS – IT’S WARP SPEED. WE’RE WORKING CLOSELY WITH FERC ON THIS PHASE OF THE PROJECT AS WELL AS TO ENSURE IT PROVIDES LOTS OF INFORMATION TO THE PUBLIC BEFORE OPEN SEASON PACKAGES ARE DELIVERED SO THAT YOU, THE PUBLIC, WILL UNDERSTAND WHAT FERC IS REVIEWING AND WHAT YOU WILL BE ASKED TO COMMENT ON BEFORE THE COMMISSION VOTES TO ALLOW THE OFFERING TO PROCEED.
WE’VE ESTABLISHED A TECHNICAL REVIEW TEAM COMPRISED OF TECHNICIANS, FEDERAL AND STATE AGENCY EXPERTS AND CANADIAN EXPERTS TO:
• SHARE ENGINEERING INFORMATION AND EXPERTISE RELEVANT TO AGENCY
PERMITTING OF DESIGN AND CONSTRUCTION OF THE ARCTIC NATURAL GAS PROJECT
• IDENTIFY PROJECT TECHNICAL ISSUES TO INCLUDE BUT NOT LIMITED TO:
PIPELINE, PROXIMITY, SECURITY, LEAK PREVENTION, BEST AVAILABLE CONTROL
TECHNOLOGY, PERMAFROST, GAS TREATMENT PLANT, AND EMISSIONS.
• IDENTIFY ISSUES THAT REQUIRE EXPEDITED COORDINATION AND RESOLVE THESE ISSUES BEFORE IMPACTING THE TIMELINE OR PROJECT.
ONE OF THE MOST AMBITOUS EFFORTS ON OUR ‘TO DO’ LIST IS THE DEVELOPMENT OF A PROTOTYPE GEOGRAPHIC INFORMATION SYSTEM.
AS YOU KNOW, THE ARCTIC IS NOT WELL MAPPED. IN FACT, THERE’S NO ACCESSIBLE STANDARD SET OF MAPS AND DATA FOR THE PIPELINE ROUTE. BUT BY THE END OF THE YEAR, WE’LL HAVE INFORMATION ON A 20-MILE STRETCH OF THE ROUTE AT ATIGUN PASS.
AGENCIES USE DIFFERENT SETS OF INCOMPATIBLE DATA. THERE IS A LACK OF AN AUTHORITATIVE BASEMAP TO REFERENCE INFORMATION RELEVANT TO PERMITTING. THERE IS
SOME GOOD DATA, BUT ALSO SOME THAT IS EITHER INCOMPLETE OR ACTUALLY INCORRECT. INTEGRATION CAN BE CHALLENGING.
OUR GOAL IS TO DEMONSTRATE THAT THE GIS PROTOTYPE IS AN AUTHORITATIVE, CONSISTENT, AND INTEGRATED SOURCE OF INFORMATION TO CONSTRUCT, OPERATE, AND MAINTAIN A GAS PIPELINE.
AS SHOWN HERE, EXISTING ELEVATION DATA FOR THE AREA IS COARSE. LIDAR DATA REVEALS THE TERRAIN IN FAR MORE DETAIL. WE HOPE TO BUILD A SYSTEM THAT USES THE INCREDIBLY DETAILED LIDAR AS THE BASE MAP.
HERE IS A DETAIL VIEW OF ATIGUN PASS, AND THE LIDAR DATA THAT WE COLLECTED THIS FALL HAS BEEN ANALYZED IN GIS TO SHOW SLOPE. HERE IS SHOWN SLOPE IN DEGREES, BLUE COLOR BEING FROM 0—7 DEGREE SLOPES; AND RED COLOR 7—90 DEGREE SLOPES. THE INTENSITY OF COLOR REFLECTS SLOPE STEEPNESS. ALSO SHOWN HERE ARE THE ORIGINAL NW BOREHOLES. MORE THAN 1,000 BOREHOLES WERE DIGITIZED AS PART OF THIS PROTOTYPE PROJECT, WHICH IS ONLY 20 MILES LONG.
THE WEB BROWSER APPLICATION PROVIDES OPEN ACCESS TO THE GIS DATABASE. DATA CAN BE SELECTED TO BE DISPLAYED DEPENDING ON LEVELS OF CONFIDENTIALITY. IN THIS CASE WE ARE LOOKING AT THE OVERVIEW OF THE ATIGUN PASS PROTOTYPE AREA ON TOP OF THE REGIONAL ELEVATION BASE OVERLAID WITH SATELLITE IMAGERY. THE TABLE OF CONTENTS FRAMES ON THE LEFT SHOWS THE ATIGUN PASS PROTOTYPE LAYERS. THESE ARE BY DEFAULT TURNED OFF AT THE BEGINNING AND CAN BE TURNED ON ONE BY ONE. NOTE, THAT EACH LAYER WILL HAVE its OWN SECURITY/CONFIDENTIALITY LEVEL. IT IS OUR GOAL TO MAKE AS MUCH INFORMATION AVAILABLE TO THE PUBLIC AS POSSIBLE.
NW BOREHOLE LOGS ARE GEOREFERANCED INTO THE GIS PROTOTYPE AND PROVIDES A STRATIFICATION OF SOIL TYPES AND PERMAFROST DATA.
WITH GIS, YOU CAN CLICK ON ANY POINT ALONG THAT STRETCH OF THE PIPELINE TO EXTRACT AND VIEW RELEVANT MAPPING AND REPORT DATA. THE POWER OF GIS IS PROVIDING A PLATFORM FOR SHOWING MANY TYPES OF INFORMATION.
IN THIS CASE WE ARE CLICKING ON A STREAM CROSSING POINT (IN GREEN SQUARES) TO PULL UP A PHOTO. WE THEN CAN CLICK ON A STREAM TO GET INFORMATION ABOUT THAT STREAM, ITS NAME AND ESSENTIAL FISH HABITAT. THE PIPELINE IS SHOWN IN RED, THE PROPOSED GASLINE MILEPOSTS IN YELLOW.
I’D LIKE TO GIVE YOU A SNEAK PREVIEW OF WHAT THE GIS WILL LOOK LIKE. IT’S A 1 MINUTE VIDEO WITH A GOOGLE EARTH FEEL. THE MOVIE FILE CONTAINS THE LIDAR, THE BOREHOLE SAMPLES ILLUSTRATED BY THE GREEN PLUS SIGNS AND THE SOIL TYPE INFORMATION, WHICH IS OVERLAIN IN PASTEL.
TO SUMMARIZE, THE GIS PROTOTYPE WILL PROVIDE AN
 AUTHORITATIVE BASEMAP, WHICH ALLOWS DATA TO BE INTEGRATED
FOR MULTIPLE AGENCIES, THE PUBLIC AND STAKEHOLDERS
• THE WEB INTERFACE PROVIDES TRANSPARENT ACCESS TO DATA AT
DIFFERENT LEVELS
LIDAR COUPLED WITH GOOD IMAGERY PROVIDES A VALUE-ADDED DATABASE. OUR NEXT STEP IS TO ACQUIRE INPUTS FROM FEDERAL AND STATE AGENCIES.
SO, THESE ARE SOME OF THE TASKS ON OUR PLATE FOR THE NEXT SIX MONTHS, AND AS THE APPLICANTS HEAD TOWARD OPEN SEASON, WE ARE WORKING DILIGENTLY WITH THE STATE OF ALASKA, CANADIAN GOVERNMENT AND ALL THE STAKEHOLDERS FROM NATIVE GROUPS TO OUR FRIENDS IN THE CONSERVATION COMMUNITY.
LET ME TAKE A MINUTE TO BRIEF YOU ON MY WORK WITH OUR CANADIAN PARTNERS. IT’S IN OUR BEST INTEREST TO ENSURE THE PROCESS MOVES AS EXPEDITIOUSLY AS POSSIBLE ON THEIR SIDE OF THE BORDER.
I’VE MADE MANY TRIPS TO CANADA IN AN EFFORT TO ENGAGE THEIR ENTHUSIASTIC RESPONSE TO THE PROJECT. THAT’S NOT AS SIMPLE AS IT MIGHT SOUND SINCE THERE ARE MANY CANADIAN WHO CONSIDER OUR PROJECT A COMPETITOR TO THEIR DREAM OF A MAKENZIE PIPELINE.
AT THIS POINT, EVERYONE IS ENGAGED. MINISTER JIM PRENTICE – WHO HAS THE ALASKA PIPELINE FILES ON HIS DESK – NATURAL RESOURCES MINISTER LISA RAITT, DEPUTY MINISTER CASSIE DOYLE, THE NATIONAL ENERGY BOARD, THE NORTHERN PIPELINE OFFICE, THE MPMO, THE ENVIRONMENTAL ASSESSMENT AGENCY, PROVINCIAL PREMIERS, THE FEDERAL SENATE, THE PETROCHEMICAL INDUSTRY, ORGANIZED LABOR, FIRST NATIONS, ET AL ARE ENGAGED AND ENTHUSIASTIC ABOUT THE ECONOMIC BENEFITS THAT THE PIPELINE WILL BRING TO CANADA.
WE’VE INVITED CANADIANS TO BE A PART OF THE TECHNICAL REVIEW TEAM – THEY HAVE EXPERTS AND EXPERIENCE THAT WILL BE OF CRITICAL IMPORTANCE TO THE U.S. PERMITTING AGENCIES. WE NEED TO HARMONIZE OUR STANDARDS – AND THAT WORK HAS ALREADY BEGUN.
ALL THOSE CANADIAN OFFICIALS I MENTIONED HAVE SHAKEN MY HAND AND PLEDGED TO MEET THE U.S. SCHEDULE SO THAT THEIR LICENSE IS IN PLACE WHEN OURS IS, IN 2014.
CANADA DOESN’T HAVE A POSITION LIKE MINE, BUT MINISTERS PRENTICE AND RAITT HAVE BEEFED UP THE MPMO TO BE THE PROJECT MANAGER FOR DENALI AND REPOPULATED THE NORTHERN PIPELINE OFFICE TO OVERSEE THE FOOTHILLS PROJECT, NOW OWNED BY TRANSCANADA, PARTNERED WITH EXXON.
WE HAVE DRAFT SURVEILLANCE AND MONITORING AGREEMENT WITH THE STATE OF ALASKA, WHICH IS REQUIRED BY OUR STATUTE, AND THE ATTORNEYS ARE WORKING TO COMPLETE IT AS SOON AS POSSIBLE. WHEN FINALIZED, THE MOU WILL LAYOUT THE PROCESS IN DETAIL FOR WORKING TOGETHER FROM THE PERMITTING PHASE OF THE PROJECT THROUGH CONSTRUCTION.
THERE ARE MAJOR INFRASTRUCTURE NEEDS THAT I’VE SPOKEN ABOUT PREVIOUSLY.
THERE IS NATIONAL SUPPORT FOR THE PIPELINE PROJECT INCLUDING AN ENDORSEMENT FROM THE NATIONAL AFL-CIO BECAUSE OF THE JOBS IT WILL CREATE, AND FOR THAT WE ALL OWE OUR GRATITUDE TO VINCE BELTRAMI. THERE’S SUPPORT FROM CONGRESS AND THE FEDERAL EMPLOYEES AT THE AGENCIES ARE EXCITED TO BE WORKING ON SUCH AN IMPORTANT PROJECT.
DECISIONS MADE ON ENERGY OVER THE NEXT TWO YEARS WILL HAVE PROFOUND IMPACTS FOR DECADES TO COME. IT IS IMPERATIVE THAT ALASKANS UNITE TO PORTECT OUR STATE DURING THE ENERGY AND CLIMATE CHANGE DEBATES TO COME.
I THINK YOU’LL AGREE WITH ME THAT THERE IS AND ALWAYS WILL BE CONSUMER DEMAND FOR ENERGY. THAT’S NATURAL GAS – CLEAN BURNING AND ENVIRONMENTALLY FRIENDLY – OUR TIME IS NOW.
CAMBRIDGE ENERGY RESEARCH ASSOCIATES HAS A GOOD STATEMENT THAT I WANT TO SHARE WITH YOU: “HUMANS HAVE THE CAPACITY TO INVENT GADGETS THAT HAVE TO BE CHARGED FASTER THAN WE INVENT NEW WAYS TO CREATE THE POWER.”
NO MATTER WHICH HORSE YOU BET ON, IT’S TIME TO BUILD THE PIPELINE SO THAT WE CAN CREATE THE POWER SOURCE TO CHARGE ALL THOSE GADGETS THAT WE USE EVERY DAY AND CAN’T SEEM TO LIVE WITHOUT.
2018 FIRST GAS SEEMS LIKE A LONG WAY AWAY, BUT 2014 FOR FINANCING AND SANCTIONING IS RIGHT AROUND THE CORNER.
I WANT TO PERSONALLY THANK THE HIGHLY PROFESSIONAL STAFF AT DENALI FOR THEIR TIRELESS EFFORTS. LISA PEKICH AND GUS GUSTAFSON WERE THERE FIRST: WE’VE SHARED SOME GROWING PAINS.
TRANSCANADA IS THE MOST SUCCESSFUL PIPELINE COMPANY IN NORTH AMERICA WITH ENGINEERS WHO, FOR 30 YEARS, HAVE BEEN DREAMING ABOUT THIS PROJECT.
I ALSO WANT TO THANK EXXON MOBIL FOR COMING TO THE TABLE. ITS RE-ENTRY IS COMMENDABLE AND ITS TECHNICAL EXPERTISE UNSURPASSED.
THERE’S NEVER BEEN A BETTER GROUP WORKING TO MAKE THIS PROJECT FINALLY HAPPEN!
I ALSO WANT TO THANK AND PRAISE THE MEN AND WOMEN WHO ARE FEDERAL EMPLOYEES, ESPECIALLY THE CAREER FEDERAL EMPLOYEES, FOR THEIR ENTHUSIASM AND HARD WORK. AND I WANT TO PUBLICLY THANK THE STATE OF ALASKA AND THE GOVERNMENT OF CANADA FOR THEIR EFFORTS.
AND, OF COURSE, I FEEL THE NEED TO ONCE AGAIN PRAISE THE MEN AND WOMEN OF THE OFC WHO HAVE GELLED INTO THE BEST TEAM ON THE PLANET – BAR NONE.
LASTLY, I THANK YOU, ALASKA AND HER PEOPLE, FOR ALLOWING ME TO WORK FOR YOU EVERY DAY FOR THE PAST 25 YEARS. EVERY DAY HAS BEEN AN ADVENTURE.
KNOW THAT I WON’T STOP NOW – MY PASSION FOR MY STATE, MY COUNTRY AND THIS PROJECT HASN’T DIMINISHED. MY RESIGNATION IS SIMPLY A FORK IN THE ROAD – FULL OF OPPORTUNITY AND I LOOK FORWARD TO THE NEXT CHAPTER.
DAVE HOLT HAD THE BEST LINE OF THE CONFERENCE WHEN HE SAID: “THE ROAD TO ENERGY SECURITY IS THROUGH ALASKA!”
LET ME EXPAND ON THAT... THE ROAD TO ENERGY SECURITY, ECONOMIC SECURITY AND DOMESTIC HOMELAND SECURITY FOR AMERICA ALL RUN THROUGH ALASKA.
SO LET’S WORK TOGETHER TO MAKE SURE THAT OUR PLACE AS THAT ROAD IS PROTECTED.
AS THE GOVERNOR SAID LAST WEEK, OUR BEST RESOURCES ARE OUR CHILDREN. ALL OF OUR EFFORTS ARE FOR THEM.
FOR THOSE OF YOU WHO HAVEN’T SEEN HER FOR AWHILE, HERE’S MINE. THIS IS TATE HANNA AT 15.
I WILL CONTINUE THE ALASKA ADVENTURE FOR HER AND FOR YOUR FUTURE.
THANK YOU.

Attachments: 

DP Oil and Gas Congress Speech 2009.09.15

Document Type: 
Speech
Release Date: 
09/15/2009

THE ALASKA NATURAL GAS PROJECT
Presented Sept. 15, 2009
To The Oil & Gas Congress
Anchorage, AK

Drue Pearce
Federal Coordinator
Office of the Federal Coordinator
Alaska Natural Gas Transportation Projects


Good afternoon, and thanks for the kind invitation to be with you again to discuss getting Alaska’s natural gas to market, and specifically what we’ve been doing in the Office of the Federal Coordinator to help make that happen.
Over the course of its lifetime, this project is estimated to create tens of thousands of good paying jobs, and in today’s economy that represents a very bright spot.
Of course, the clean natural gas it will deliver will help the nation tremendously as we transition to renewable sources of energy.
For these reasons, and many more, we’re fortunate to have broad support for the project from the Obama Administration, the Congress, from the State of Alaska and, of course, from the industry, which will build and fill this pipeline.
This week my Director of Permits, Scheduling and Compliance is at the annual AFL-CIO meeting in Pittsburgh to work with labor on the importance of the pipeline in creating jobs for Americans. And, as may be no surprise, the Alaska Natural Gas Pipeline is one of the topics of the day.
This morning, Vince Beltrami, the President of the Alaska AFL-CIO spoke before the national convention to all of labor about the importance of this gas pipeline project and the amount of renewable energy projects that exist and are being created in Alaska. Vince told thousands of convention goers that this project will create tens of thousands of jobs across our nation, from the manufacturing of steel pipe and other integral parts, to transportation, loading, shipping, and delivery of those parts. He explained that under Alaska law, AGIA, the construction of the Alaska natural gas pipeline will be subject to a Project Labor Agreement. And finally, Vince expressed that natural gas is a clean, reliable and domestically produced energy source.
Vince's speech received a huge reception because on a national level the AFL-CIO working families get it.
To prove that point, the Second District Vice President of the International Brotherhood of Electrical Workers, which represents all of New England, today came out in support of the project. He said even though the project would be constructed thousands of miles away from the East Coast, “the jobs set the stage for the next generation of workers."
As all of Alaska’s leaders – both at the Congressional level and the state level – and now national labor unions know, Alaska’s natural gas is the “it fuel” of today’s global economy; perhaps not as “it” as Paris Hilton, but in the context of clean, secure, available, low cost and green, we are a happening source for today’s and tomorrow’s energy supply.
This has been an active year for the pipeline project. TransCanada Alaska and ExxonMobil formed a new project partnership. Both Denali (the BP/ConocoPhillips partnership) and TransCanada Alaska have entered the FERC Pre-file Process and FERC designated Argonne National Laboratory as the third party contractor for the Denali project. At the OFC, we’re doing our part to move the project forward.
As many of you know, we signed a Memorandum of Understanding three years ago to strengthen coordination with all the federal agencies that have permitting functions related to this project and create a consolidated project and implementation plan.
We need to make sure that these agencies are working together, that they are moving forward with their respective assignments and that they have the necessary knowledge and the most reliable information about the project as possible.
We work daily to ensure accurate and in-depth communication between all parties, and we coordinate with the Canadian federal, territorial and provincial governments as well as all stakeholders, including tribal interests, the Congress, and the State.
One of our first accomplishments this year was the completion of the First Phase Consolidated Implementation Plan for the Denali project in June. We’ll do one for each applicant that enters the FERC Pre-file Process. So, we’ve finished the first phase of the Denali plan and will have the first phase of the TransCanada Alaska/ExxonMobil plan done by the end of the year.
In August, my office hosted eight White House and agency officials on a trip to the state to learn more about the pipeline and the route that it will follow.
Our guests were all critical members of the federal team involved in getting the pipeline built – Acting Deputy Administrator for the Pipeline and Hazardous Materials Safety Administration, a member of the TSA Pipeline Security Division, a member of the Advisory Council on Historic Preservation and the State Historic Preservation Officer, members from DOD and Army Corp of Engineers staff including the new Alaska head, Colonel Koenig, staff for the Department of the Interior’s Office of the Secretary, and finally, two members of the White House’s team, the NEPA lead at the Council on Environmental Quality and the Energy Director for the National Security Council.
It was a great opportunity for me and my staff to educate our travelers about the project, including our federal agency partners and their activities, so we can move it forward together.
In addition to our trip, this summer Alaska hosted a number of federal dignitaries and staff. Four cabinet secretaries who, along with Gov. Parnell and Senator Begich, visited rural Alaska to learn more about climate change and rural issues.
The Federal Energy Regulatory Commission and Environmental Protection Agency each sponsored a trip to meet with agencies that are part of the federal interagency team and the Alaska Department of Natural Resources.
Also this summer members of my staff traveled the Dalton Highway accompanied by FERC and EPA staff. They observed the entire route north from Fairbanks and spent significant time examining road conditions, bridges, river crossings and other infrastructure.
The surveyed pinch points such as the Yukon River and Atigun Pass. In Prudhoe Bay, they visited the West Dock, sand and gravel locations and toured the proposed location of the gas treatment plant.
There was also an arctic tour by the head of NOAA, the Deputy Secretary of the Department of the Interior, the U.S. Coast Guard Commandant and the Chair of the White House Council on Environmental Quality to study coastal erosion and the oceans as the first step in establishing a new comprehensive ocean policy.
So, in effect, we’re creating our own information pipeline from the arctic to Washington, D.C. in preparation for the final push to get permitting in place and get the natural gas pipeline construction going.
President Obama has told us that getting a natural gas pipeline built is one of his priorities and having the President’s support is important for moving it along.
I don’t need to remind this audience that the project concept has spanned six presidents, seven Alaska governors, eight Canadian Prime Ministers including Pierre Trudeau twice! There have been countless proposals to produce North Slope gas since the late 1970’s.
Ironically, not far from where our lawmakers meet in the Capitol, there are these busses that ferry people around D.C., and I got a kick out of seeing a bus sign that says “this bus runs on clean natural gas.”
Our message is being delivered by everyday citizens right under the nose of lawmakers who are considering a climate change bill that needs to be friendly to natural gas development.
To keep America running on abundant natural gas, which is now being touted as the bridge fuel of the 21st century, we have to pay attention to every piece of legislation and Federal agency proposed rule making that might impact the project.
As I meet with members of Congress and their staff, they continue to ask the question “what can we do to help?” And my response is that their most important action is to make sure any legislation they pass will do no harm. As they work on energy and climate legislation, they need to be careful to not negatively impact the nation’s ability to gain the benefits of Alaska’s natural gas through this pipeline.
One goal of Congress is to reduce CO2 and other harmful emissions. Using natural gas, a clean burning and cost effective source of energy is a great way to do just that. This project will deliver approximately 4.5bcf of natural gas each day to the lower 48 states. That is a lot of clean natural gas that can fill existing and upcoming energy demand.
Congress also must be mindful to maintain a level playing field by ensuring that natural gas can compete fairly in our energy markets. And, as the Senate creates its climate and energy legislation, it should listens to Alaskan colleagues, Senators Murkowski and Begich. The Senators are working together to bolster the use of natural gas, the cleaner burning fossil fuel, as well as understand the moderate and potentially negative financial impacts to all natural gas pipelines, including this project, of the cost of CO2 allowances on combustion emissions and compliance with performance standards for fugitive emissions.
Congressional actions to date have been very helpful. The Senate Energy and Natural Resources Committee recently passed a bill that included loan guarantee language that will increase the project federal guarantee to $30 billion, and make sure that whichever company applies can receive 80 percent of the project cost. Both these changes are helpful to ensuring the economics of this privately financed project.
As for other OFC actions, we recently opened an Alaska office here in Anchorage headed by my Deputy, Admiral Tom Barrett, who prior to this job was the Deputy Secretary at the Department of Transportation and prior to that was the Administrator of the U.S. Pipeline and Hazardous Materials Safety Administration; the office also includes Christa Gunn, our environmental engineer.
In Washington, our staff includes a permitting chief, a communications staff and administrative support along with our general counsel.
As I mentioned earlier, we work closely with the state agencies in Alaska, with Canadian authorities as well as with every stakeholder.
We’ve begun negotiations with the State of Alaska on a joint Monitoring and Surveillance Agreement to oversee construction of the project.
We’re also in the process of developing a prototype Geospatial Information System, GIS, along a 20-mile stretch of the proposed pipeline route at Atigun Pass. We recently conducted a Light Detection and Ranging, LiDAR, shoot along the pass and hope to have the prototype done by the end of the year. If successful, we’ll propose the system for the entire 750-mile pipeline route from Prudhoe Bay to the Canadian border.
This system will provide the most consistent source of information and mapping for the pipeline project. Using LiDAR technology to create a base map, the GIS will offer a range of existing documents, studies and research from private sector and government sources to create a web-based data source that can be used not only by federal and state agencies involved in permitting the gas pipeline but also the public.
This is critical because right now, agencies use different sets of data and systems when studying the pipeline route, and those data sets are not compatible. The new resource system will erase those inconsistencies and incompatibilities by giving every agency involved in the pipeline project use of the same geospatially referenced baseline data on fault and landslide hazard detection, wetlands, and river crossing in order to lay a foundation for consistent, effective and streamlined permitting activities and land and resource management.
On the diplomatic front, since spring we’ve met with government leaders in Canada multiple times on key issues ranging from workforce development on both sides of the border to mapping out how to coordinate critical permitting timelines.
Tom Barrett and I met in early June with Michael Wilson, Canadian Ambassador to the United States and later that month we met with the heads of agencies including Natural Resources Canada, the Major Projects Management Office, the Canadian Environmental Assessment Agency and the Northern Pipeline Agency on myriad issues.
As you may know, the U.S. and Canada are both going through a transition in the appointment and confirmation of new Ambassadors. My office will continue to work with the new appointees just as we have with their predecessors.
Positive working relations between the U.S. and Canada are essential to resolving key cross-border issues. For example, we are working with both the U.S. Pipeline and Hazardous Materials Safety Administration and the Canadian National Energy Board to standardize requirements on both sides of the border to withstand the extreme Arctic conditions. These relations also provide us with opportunities to discuss how the Alaska pipeline can coexist with and potentially benefit from smaller pipeline projects in Canada, such as the Mackenzie Gasline Project in the Northwest Territories. Permitting and timeline issues and the development of infrastructure and employment on both sides of the border are important issues we discuss regularly.
While we’re dealing with these issues at the national level, there also are major challenges at the state level.
The most critical for the immediate future are the challenges that face the State of Alaska in developing both its workforce and its infrastructure that must be taken into consideration to make this project possible.
As I have discussed in years past and FERC noted in its latest report to Congress, in order to construct a pipeline, it is imperative to have the necessary infrastructure in place to stage all the manpower and materials for construction.
There are a number of projects to be done. The State and companies are working together to identify and prioritize State projects that the State can improve such as bridges, highways, airports, material sites and maintenance camps that might be used to support tens of thousands of workers, the heavy equipment and the 2.5 million tons of steel needed to construct the pipeline.
The latest estimate of projects the state identified for completion before construction begins outlines $2 billion dollars in projects.
But it will take 4-6 years to complete all the projects, and they must be committed to by the state legislature.
Every day, week, month, year that we wait to build the infrastructure adds major costs to the project. We can’t afford unnecessary delays.
And then there is the challenge of finding, training and retaining the labor pool needed on both sides of the border. Labor for the Trans Alaska Pipeline System peaked during its construction at 28,000 workers with over 70,000 jobs created between 1975 and 1978, and that was just for construction.
As I mentioned earlier, at its peak this pipeline will require tens of thousands of skilled workers. This skilled labor force must be trained, be ready to be hired, and then retained throughout the preconstruction and construction. A major focus on the training must be giving the workers job skills that can be used beyond the construction of a pipeline.
The U.S. Dept. of Labor gave the State of Alaska a grant it’s using to conduct a study as well as to begin finding and training that labor pool.
Alaska Department of Labor Commissioner Click Bishop and Vince Beltrami both spoke to our August visitors explaining their efforts to date to ensure we have a prepared workforce.
The State of Alaska and the Government of Canada also have approval processes that must proceed alongside the U.S. federal licensing and permitting process.
In some respects, the Canadian coordination is the most important part of the process because the pipeline will traverse more than a thousand miles through remote Canada.
In the U.S., ANGPA designates the FERC as the lead agency for completing the environmental review, or EIS, and allows 18 months to do it. In my conversations with Minister Prentice in Canada and Governor Parnell, both have agreed to time their processes to coincide with the aggressive schedule set by the U.S. Congress.
The schedule is very demanding, especially if two applicants proceed with a separate EIS.
Nevertheless, all federal agencies have been working diligently during the Pre-File Process preparing for the EIS. That work, the Implementation Plans the OFC is preparing, and the interagency meetings my office hosts should ensure the federal agencies can meet the aggressive schedule.

I have to tell you that expediting this confluence of interests and the permitting and technical issues may seem daunting. I like to think of it as multitasking at its finest.
But I do love a good challenge and want to ensure a transparent process that brings a more predictable, accountable and timely regulatory review process and construction for this project.
When the process seems slow, I’m reminded of Winston Churchill who advised to never, never, never give up.
You might know that it was Churchill who, as Lord of the Admiralty and a member of the War Council of Great Britain, negotiated to acquire a majority interest in the Anglo-Persian Oil Company in 1914. That deal brought the company under British government control and secured its access to Persian oil. That company later became British Petroleum.
When I look at the complexity of our gas pipeline project, and all of the competing and complementary interests, I’m reminded of Churchill’s foresight in bringing energy security to Great Britain and of his words, which I leave you with today:
He said: “Success is not final, failure is not fatal; it is the courage to continue that counts.”
This project is great for the economy, for the environment, for Alaska and it’s great for America.
With the kind of broad support we’re seeing from the President, the Congress and from labor as recently as today, we’re more than hopeful that we will be delivering abundant arctic natural gas to North American markets within nine years, but we must continue to work diligently to deliver that dream.
Thank You

Attachments: 

2009 Performance and Accountability Report

Document Type: 
Federal Reports
Release Date: 
11/10/2009

We are pleased to present the Office of the Federal coordinator for Alaska Natural Gas Transportation Projects' (OFC) second annual Performance and Accountability Report. This report includes highlights of the agency's  ission, goals,organizational structure, activities for FY2009, and a summary of our sterardship efforts.

Attachments: 

2008 Performance and Accountability Report

Document Type: 
Federal Reports
Release Date: 
11/17/2008

Federal Coordinator Pearce is pleased to present the OFC’s first Performance and Accountability Report (PAR). This report includes highlights of the agency’s goals and accomplishments for FY2008 as well as details of the OFC’s operations since start up began in January 2007. The Federal Coordinator is also pleased to announce an "unqualified finding" (clean) in the agency’s first audit.

Attachments: 
Syndicate content